CPWD Analysis of Rates · Road Work

Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete

Item number
16.42
Analysis basis
Details of cost for 1.00 cum.
Priced inputs
13
Derived rate
7,993.80 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.42 Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete — is derived from 13 priced inputs for 1.00 cum and works out to ₹7,993.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Side shuttering
  • Taking the slab to be 5cm thick and width
  • to be 6 metre, length of road 27 metre =
  • 9.90/24.30 = 0.407 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
0293Stone Aggregate (Single size) : 40 mm nominal sizeMaterialcum0.521,400.00728.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.221,425.00313.50
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.111,400.00154.00
0982Coarse sand (zone III)Materialcum0.4451,450.00645.25
0367Portland Cement (OPC-43 grade)Materialtonne0.325,156.001,649.92
0155Mason (average)Labourday0.1857.0085.70
0114BeldarLabourday1.63736.001,199.68
0101BhistiLabourday0.7816.00571.20
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.077900.0069.30
0012Vibrator (Needle type 40 mm)Machineryday0.07400.0028.00
9999SundriesMaterialL.S.262.2759.02
Rate as per item no 5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysissqm0.407392.15159.61
9999SundriesMaterialL.S.1.432.273.25
TOTAL
5,666.43
Add 1 % Water charges on “W-A”
55.07
TOTAL
5,721.50
Add GST on “X-A” (multiplying factor 0.2127)
1,183.01
TOTAL
6,904.51
Add 15% CPOH on “Y-A”
1,011.74
TOTAL
7,916.25
Add Cess @ 1% on “Z-A”
77.57
Cost for 1 cum.
7,993.82
Say
7,993.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1206. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.