Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete

Item number
16.42
Analysis basis
1.00 cum
Priced inputs
13
Derived rate
₹7,993.80/ CUM
D-01/RATE ANALYSISITEM 16.42

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.42 (Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete) is derived from 13 priced inputs for 1.00 cum and works out to ₹7,993.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Side shuttering
  • Taking the slab to be 5cm thick and width
  • to be 6 metre, length of road 27 metre =
  • 9.90/24.30 = 0.407 sqm
ANALYSIS OF RATES · ITEM 16.42DETAILS OF COST FOR 1.00 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0293MATStone Aggregate (Single size) : 40 mm nominal sizecum0.521,400.00728.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.221,425.00313.50
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.111,400.00154.00
0982MATCoarse sand (zone III)cum0.4451,450.00645.25
0367MATPortland Cement (OPC-43 grade)tonne0.325,156.001,649.92
0155LABMason (average)day0.1857.0085.70
0114LABBeldarday1.63736.001,199.68
0101LABBhistiday0.7816.00571.20
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.077900.0069.30
0012MACHVibrator (Needle type 40 mm)day0.07400.0028.00
9999MATSundriesL.S.262.2759.02
SUBRate as per item no 5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1sqm0.407392.15159.61
9999MATSundriesL.S.1.432.273.25
BUILD-UP TO RATE
TOTAL
5,666.43
Add 1 % Water charges on “W-A”
+55.07
TOTAL
5,721.50
Add GST on “X-A” (multiplying factor 0.2127)
+1,183.01
TOTAL
6,904.51
Add 15% CPOH on “Y-A”
+1,011.74
TOTAL
7,916.25
Add Cess @ 1% on “Z-A”
+77.57
Cost for 1 cum.
7,993.82
SAY
₹7,993.80
D-02/SOURCEPRINTED PAGE 1206
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1206

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1206. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.