4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately)

With Refinery Modified Bitumen CRMB 55 conforming to IRC: SP : 53

Item number
16.39.3
Analysis basis
Details of cost for 100sqm.
Priced inputs
21
Derived rate
528.65

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.39.3 4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately) : With Refinery Modified Bitumen CRMB 55 conforming to IRC: SP : 53 — is derived from 21 priced inputs and works out to ₹528.65 after water charges, GST, CPOH and cess. The full build-up is below.

  • @56kg. per cum. of aggregate and 128kg.
  • per cum. of sand:
  • 56x2.60=145.6kg. = 0.146t +
  • 128x2.60 = 332.8kg = 0.333t
  • Total = 0.479 tonne
  • 0.70kg.x479=33.53kg.
  • Steam coal for heating bitumen @ 2 qunitals
  • per tonne of bitumen = 2x0.479=0.958q
  • Labour for cleaning road surface, heating
  • bitumen mixing and spreading aggregate :
  • (a) For cleaning :
  • (b) For heating bitumen :
  • (c) For cleaning, mixing and spreading premix aggregate :
  • (d) Consolidation charges :
  • (e) Misc :
  • (with thick wire)
CodeInputUnitQuantityRate (INR)Amount (INR)
7739Modified Bitumen Refinary produced CRMB - 55Modified Bitumen Refinery produced CRMB - 55Materialtonne0.47933,100.0015,854.90
2914SolventMaterialkilogram33.5332.001,072.96
2910Stone chippings/ screenings 12.5/ 13.2 mm nominal sizeMaterialcum1.561,400.002,184.00
2911Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterialcum1.041,400.001,456.00
0982Coarse sand (zone III)Materialcum2.61,450.003,770.00
0370Coal (steam)Materialquintal0.958500.00479.00
0128MateLabourday0.16816.00130.56
0114BeldarLabourday1.4736.001,030.40
0115CoolieLabourday1.4736.001,030.40
0114BeldarLabourday1.88736.001,383.68
0130MistryLabourday0.31897.00278.07
0114BeldarLabourday9.46736.006,962.56
0113ChowkidarLabourday0.45736.00331.20
0101BhistiLabourday0.18816.00146.88
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.183,350.00603.00
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.3900.00270.00
0023Hot Bitumen mixer 0.5 cum i/c hand cartMachineryday0.033,950.00118.50
0364Wire brushMaterialeach0.0925.002.25
0365Soft brushMaterialeach0.2725.006.75
9999Brooms and gunny bagsMaterialL.S.5.332.2712.10
9999SundriesMaterialL.S.16.122.2736.59
TOTAL
37,159.80
Add 1 % Water charges on “W”
371.60
TOTAL
37,531.40
Add GST on “X” (multiplying factor 0.2127)
7,982.93
TOTAL
45,514.33
Add 15% CPOH on “Y”
6,827.15
TOTAL
52,341.48
Add Cess @ 1% on “Z”
523.41
Cost for 100 sqm.
52,864.89
Cost per sqm.
528.65
Say
528.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1203. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.