4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately)

With paving asphalt grade VG - 30 with no solvent
Item number
16.39.2
Analysis basis
Details of cost for 100sqm.
Priced inputs
20
Derived rate
₹568.60
D-01/RATE ANALYSISITEM 16.39.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.39.2 (4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately) : With paving asphalt grade VG - 30 with no solvent) is derived from 20 priced inputs and works out to ₹568.60 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • @56kg. per cum. of aggregate and 128kg.
  • per cum. of sand:
  • 56x2.60=145.6kg. = 0.146t +
  • 128x2.60 = 332.8kg = 0.333t
  • Total = 0.479 t
  • Labour for cleaning road surface, heating
  • bitumen mixing and spreading aggregate :
  • (a) For cleaning :
  • (b) For heating bitumen :
  • (c) For cleaning, mixing and spreading
  • pre-mix aggregate :
  • (d) Consolidation charges :
  • (e) Brushes etc. for cleaning :(with thick wire)
ANALYSIS OF RATES · ITEM 16.39.2DETAILS OF COST FOR 100SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7309MATPaving Asphalt VG-30 of approved qualityPaving Asphalt of grade VG-30 of approved qualitytonne0.47941,202.0019,735.76
2910MATStone chippings/ screenings 12.5/ 13.2 mm nominal sizecum1.561,400.002,184.00
2911MATStone chippings/ screenings 10/ 11.2 mm nominal sizecum1.041,400.001,456.00
0982MATCoarse sand (zone III)cum2.61,450.003,770.00
0370MATCoal (steam)quintal0.958500.00479.00
0128LABMateday0.16816.00130.56
0114LABBeldarday1.4736.001,030.40
0115LABCoolieday1.4736.001,030.40
0114LABBeldarday1.88736.001,383.68
0130LABMistryday0.31897.00278.07
0114LABBeldarday9.46736.006,962.56
0113LABChowkidarday0.45736.00331.20
0101LABBhistiday0.18816.00146.88
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.183,350.00603.00
0001MACHHire charges of Coaltar Boiler 900 to 1400 litresday0.3900.00270.00
0023MACHHot Bitumen mixer 0.5 cum i/c hand cartday0.033,950.00118.50
0364MATWire brusheach0.0925.002.25
0365MATSoft brusheach0.2725.006.75
9999MATBrooms and gunny bagsL.S.5.332.2712.10
9999MATSundriesL.S.16.122.2736.59
BUILD-UP TO RATE
TOTAL
39,967.70
Add 1 % Water charges on “W”
+399.68
TOTAL
40,367.38
Add GST on “X” (multiplying factor 0.2127)
+8,586.14
TOTAL
48,953.52
Add 15% CPOH on “Y”
+7,343.03
TOTAL
56,296.55
Add Cess @ 1% on “Z”
+562.97
Cost for 100 sqm.
56,859.52
Cost per sqm.
568.60
SAY
₹568.60
D-02/SOURCEPRINTED PAGE 1201
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1201

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1201. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.