4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately)

With paving Asphalt grade VG - 10 heated and then mixed with solvent at the rate of 70 grams per kg of asphalt
Item number
16.39.1
Analysis basis
Details of cost for 100sqm.
Priced inputs
21
Derived rate
₹531.60
D-01/RATE ANALYSISITEM 16.39.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.39.1 (4 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately) : With paving Asphalt grade VG - 10 heated and then mixed with solvent at the rate of 70 grams per kg of asphalt) is derived from 21 priced inputs and works out to ₹531.60 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • @56kg. per cum. of aggregate and 128kg.
  • per cum. of sand:
  • 56x2.60=145.6kg. = 0.146t +
  • 128x2.60 = 332.8kg = 0.333t
  • Total = 0.479 t
  • 0.70kg.x479=33.53kg
  • Steam coal for heating bitumen @ 2 qunitals
  • per tonne of bitumen = 2x0.479=0.958q
  • Labour for cleaning road surface, heating
  • bitumen mixing and spreading aggregate :
  • (a) For cleaning :
  • (b) For heating bitumen :
  • (c) For cleaning, mixing and spreading
  • pre-mix aggregate :
  • (d) Consolidation charges :
  • (e) Misc :
  • (with thick wire)
ANALYSIS OF RATES · ITEM 16.39.1DETAILS OF COST FOR 100SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2916MATPaving Asphalt VG -10 of approved qualityPaving Asphalt VG 10 of approved qualitytonne0.47933,530.0016,060.87
2914MATSolventkilogram33.5332.001,072.96
2910MATStone chippings/ screenings 12.5/ 13.2 mm nominal sizecum1.561,400.002,184.00
2911MATStone chippings/ screenings 10/ 11.2 mm nominal sizecum1.041,400.001,456.00
0982MATCoarse sand (zone III)cum2.61,450.003,770.00
0370MATCoal (steam)quintal0.958500.00479.00
0128LABMateday0.16816.00130.56
0114LABBeldarday1.4736.001,030.40
0115LABCoolieday1.4736.001,030.40
0114LABBeldarday1.88736.001,383.68
0130LABMistryday0.31897.00278.07
0114LABBeldarday9.46736.006,962.56
0113LABChowkidarday0.45736.00331.20
0101LABBhistiday0.18816.00146.88
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.183,350.00603.00
0001MACHHire charges of Coaltar Boiler 900 to 1400 litresday0.3900.00270.00
0023MACHHot Bitumen mixer 0.5 cum i/c hand cartday0.033,950.00118.50
0364MATWire brusheach0.0925.002.25
0365MATSoft brusheach0.2725.006.75
9999MATBrooms and gunny bagsL.S.5.332.2712.10
9999MATSundriesL.S.16.122.2736.59
BUILD-UP TO RATE
TOTAL
37,365.77
Add 1 % Water charges on “W”
+373.66
TOTAL
37,739.43
Add GST on “X” (multiplying factor 0.2127)
+8,027.18
TOTAL
45,766.61
Add 15% CPOH on “Y”
+6,864.99
TOTAL
52,631.60
Add Cess @ 1% on “Z”
+526.32
Cost for 100 sqm.
53,157.92
Cost per sqm.
531.58
SAY
₹531.60
D-02/SOURCEPRINTED PAGE 1200
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1200

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1200. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.