2.5 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 1.65 cum per 100 sqm and coarse sand @ 1.65 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately)

With paving Asphalt grade VG - 30
Item number
16.38.2
Analysis basis
Details of cost for 100sqm.
Priced inputs
20
Derived rate
₹377.05
D-01/RATE ANALYSISITEM 16.38.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.38.2 (2.5 cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 1.65 cum per 100 sqm and coarse sand @ 1.65 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc. complete. (tack coat to be paid separately) : With paving Asphalt grade VG - 30) is derived from 20 priced inputs and works out to ₹377.05 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 60/70 bitumen @56kg. per cum. of
  • aggregate and 128kg. per cum. of sand:
  • 56x1.65=92.4kg. = 0.092t +
  • 128x1.65 = 211.2kg = 0.211t
  • Total= 0.303t
  • Labour for cleaning road surface, heating
  • bitumen mixing and spreading aggregate :
  • (a) For cleaning :
  • (b) For heating bitumen :
  • (c) For cleaning, mixing and spreading
  • pre-mix aggregate :
  • (d) Consolidation charges :
  • (at barriers for night watch and for road
  • roller)
  • (e) Misc :
  • (with thick wire)
ANALYSIS OF RATES · ITEM 16.38.2DETAILS OF COST FOR 100SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7309MATPaving Asphalt VG-30 of approved qualityPaving Asphalt of grade VG-30 of approved qualitytonne0.30341,202.0012,484.21
2910MATStone chippings/ screenings 12.5/ 13.2 mm nominal sizecum0.991,400.001,386.00
2911MATStone chippings/ screenings 10/ 11.2 mm nominal sizecum0.661,400.00924.00
0370MATCoal (steam)quintal0.606500.00303.00
0982MATCoarse sand (zone III)cum1.651,450.002,392.50
0128LABMateday0.16816.00130.56
0114LABBeldarday1.4736.001,030.40
0115LABCoolieday1.4736.001,030.40
0114LABBeldarday1.19736.00875.84
0130LABMistryday0.24897.00215.28
0114LABBeldarday6.12736.004,504.32
0113LABChowkidarday0.34736.00250.24
0101LABBhistiday0.13816.00106.08
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.133,350.00435.50
0001MACHHire charges of Coaltar Boiler 900 to 1400 litresday0.21900.00189.00
0023MACHHot Bitumen mixer 0.5 cum i/c hand cartday0.053,950.00197.50
0364MATWire brusheach0.1325.003.25
0365MATSoft brusheach0.425.0010.00
9999MATBrooms and gunny bagsL.S.7.152.2716.23
9999MATSundriesL.S.8.972.2720.36
BUILD-UP TO RATE
TOTAL
26,504.67
Add 1 % Water charges on “W”
+265.05
TOTAL
26,769.72
Add GST on “X” (multiplying factor 0.2127)
+5,693.92
TOTAL
32,463.64
Add 15% CPOH on “Y”
+4,869.55
TOTAL
37,333.19
Add Cess @ 1% on “Z”
+373.33
Cost for 100 sqm.
37,706.52
Cost per sqm.
377.07
SAY
₹377.05
D-02/SOURCEPRINTED PAGE 1198
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1198

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1198. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.