CPWD Analysis of Rates · Road Work

Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy

For 50mm compacted thickness using coarse aggregate of size 50-20 mm graded @ 0.60 cum per 10 sqm key aggregate of size 12.5 mm graded @ 0.15 cum per 10 sqm. With paving asphalt grade VG - 10 @ 50 kg/ 10 sqm

Item number
16.36.1
Analysis basis
Details of cost for 370 sqm.
Priced inputs
20
Derived rate
505.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.36.1 Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy : For 50mm compacted thickness using coarse aggregate of size 50-20 mm graded @ 0.60 cum per 10 sqm key aggregate of size 12.5 mm graded @ 0.15 cum per 10 sqm. With paving asphalt grade VG - 10 @ 50 kg/ 10 sqm — is derived from 20 priced inputs for 370 sqm and works out to ₹505.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Taking stone aggregate 40mm = 45%
  • 20mm = 44%
  • 11.2mm = 8%
  • Stone dust = 3%
  • @ 50kg/10 sqm.
  • (B) Labour:
  • for spreading stone metal
  • for hand packing
  • dry rolling
  • Bajri spreader
  • for spreading key aggregate
  • for spraying bitumen
  • of power roller
  • (C) Machinery :
CodeInputUnitQuantityRate (INR)Amount (INR)
0293Stone Aggregate (Single size) : 40 mm nominal sizeMaterialcum9.991,400.0013,986.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum9.771,425.0013,922.25
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum1.781,400.002,492.00
1159Stone dustMaterialcum0.61,100.00660.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum2.331,425.003,320.25
0296Stone Aggregate (Single size) : 12.5 mm nominal sizeMaterialcum2.661,400.003,724.00
1159Stone dustMaterialcum0.561,100.00616.00
2916Paving Asphalt VG -10 of approved qualityPaving Asphalt VG 10 of approved qualityMaterialtonne1.8533,530.0062,030.50
0114BeldarLabourday16.67736.0012,269.12
0114BeldarLabourday5.33736.003,922.88
0114BeldarLabourday2.67736.001,965.12
0114BeldarLabourday1.33736.00978.88
0138Sprayer (for bitumen, tar etc.)Labourday0.67816.00546.72
0114BeldarLabourday1.33736.00978.88
0114BeldarLabourday6.67736.004,909.12
0114BeldarLabourday0.67736.00493.12
0128MateLabourday1.77816.001,444.32
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.45900.00405.00
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.613,350.002,043.50
9999Misc. items as spray nozzle, joint paper, coconut oil, country soap etcMaterialL.S.3512.27796.77
TOTAL
1,31,504.43
Add 1 % Water charges on “W”
1,315.04
TOTAL
1,32,819.47
Add GST on “X” (multiplying factor 0.2127)
28,250.70
TOTAL
1,61,070.17
Add 15% CPOH on “Y”
24,160.53
TOTAL
1,85,230.70
Add Cess @ 1% on “Z”
1,852.31
Cost for 370 Sqm.
1,87,083.01
Cost per sqm.
505.63
Say
505.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1191. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.