Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy
- Item number
- 16.36.2
- Analysis basis
- 300 sqm
- Priced inputs
- 19
- Derived rate
- ₹744.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.36.2 (Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy : For 75 mm compacted thickness in two layers using stone aggregate of size 63-41 mm graded @ 0.90 cum per 10 sqm key aggregate of size 20.0 mm graded @ 0.18 cum per 10 sqm. With paving asphalt grade VG - 10 @ 68 kg/10 sqm) is derived from 19 priced inputs for 300 sqm and works out to ₹744.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Taking output as 300 sqm. for single layer.
- Coarse agg. = 300/10x0.90 = 27 cum.
- Key agg = 300/10x0.18 = 5.4 cum.
- Bitumen = 300/10x68 = 2.04 t.
- for spreading stone metal
- for hand packing
- dry rolling
- /Bajri spreader
- for spreading key aggregate
- for spraying bitumen
- road roller
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0292 | MAT | Stone Aggregate (Single size) : 50 mm nominal size | cum | 8.1 | 1,100.00 | 8,910.00 |
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | 14.58 | 1,425.00 | 20,776.50 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size | cum | 4.32 | 1,400.00 | 6,048.00 |
| 0294 | MAT | Stone Aggregate (Single size) : 25 mm nominal size | cum | 2.05 | 1,400.00 | 2,870.00 |
| 0296 | MAT | Stone Aggregate (Single size) : 12.5 mm nominal size | cum | 2.57 | 1,400.00 | 3,598.00 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.81 | 1,400.00 | 1,134.00 |
| 2916 | MAT | Paving Asphalt VG -10 of approved qualityPaving Asphalt VG 10 of approved quality | tonne | 2.04 | 33,530.00 | 68,401.20 |
| 0114 | LAB | Beldar | day | 25 | 736.00 | 18,400.00 |
| 0114 | LAB | Beldar | day | 8 | 736.00 | 5,888.00 |
| 0114 | LAB | Beldar | day | 4 | 736.00 | 2,944.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 0138 | LAB | Sprayer (for bitumen, tar etc.) | day | 1 | 816.00 | 816.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 0114 | LAB | Beldar | day | 10 | 736.00 | 7,360.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 0128 | LAB | Mate | day | 2.65 | 816.00 | 2,162.40 |
| 0001 | MACH | Hire charges of Coaltar Boiler 900 to 1400 litres | day | 0.5 | 900.00 | 450.00 |
| 0003 | MACH | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.75 | 3,350.00 | 2,512.50 |
| 9999 | MAT | Misc. items as spray nozzle, joint paper, coconut oil, country soap etc | L.S. | 429 | 2.27 | 973.83 |
- TOTAL
- 1,56,924.43
- Add 1 % Water charges on “W”
- +1,569.24
- TOTAL
- 1,58,493.67
- Add GST on “X” (multiplying factor 0.2127)
- +33,711.60
- TOTAL
- 1,92,205.27
- Add 15% CPOH on “Y”
- +28,830.79
- TOTAL
- 2,21,036.06
- Add Cess @ 1% on “Z”
- +2,210.36
- Cost for 300 Sqm.
- 2,23,246.42
- Cost per sqm.
- 744.15
- SAY
- ₹744.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1193
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1193. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.