Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy

For 75 mm compacted thickness in two layers using stone aggregate of size 63-41 mm graded @ 0.90 cum per 10 sqm key aggregate of size 20.0 mm graded @ 0.18 cum per 10 sqm. With paving asphalt grade VG - 10 @ 68 kg/10 sqm
Item number
16.36.2
Analysis basis
300 sqm
Priced inputs
19
Derived rate
₹744.15/ SQM
D-01/RATE ANALYSISITEM 16.36.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.36.2 (Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy : For 75 mm compacted thickness in two layers using stone aggregate of size 63-41 mm graded @ 0.90 cum per 10 sqm key aggregate of size 20.0 mm graded @ 0.18 cum per 10 sqm. With paving asphalt grade VG - 10 @ 68 kg/10 sqm) is derived from 19 priced inputs for 300 sqm and works out to ₹744.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Taking output as 300 sqm. for single layer.
  • Coarse agg. = 300/10x0.90 = 27 cum.
  • Key agg = 300/10x0.18 = 5.4 cum.
  • Bitumen = 300/10x68 = 2.04 t.
  • for spreading stone metal
  • for hand packing
  • dry rolling
  • /Bajri spreader
  • for spreading key aggregate
  • for spraying bitumen
  • road roller
ANALYSIS OF RATES · ITEM 16.36.2DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0292MATStone Aggregate (Single size) : 50 mm nominal sizecum8.11,100.008,910.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum14.581,425.0020,776.50
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum4.321,400.006,048.00
0294MATStone Aggregate (Single size) : 25 mm nominal sizecum2.051,400.002,870.00
0296MATStone Aggregate (Single size) : 12.5 mm nominal sizecum2.571,400.003,598.00
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.811,400.001,134.00
2916MATPaving Asphalt VG -10 of approved qualityPaving Asphalt VG 10 of approved qualitytonne2.0433,530.0068,401.20
0114LABBeldarday25736.0018,400.00
0114LABBeldarday8736.005,888.00
0114LABBeldarday4736.002,944.00
0114LABBeldarday2736.001,472.00
0138LABSprayer (for bitumen, tar etc.)day1816.00816.00
0114LABBeldarday2736.001,472.00
0114LABBeldarday10736.007,360.00
0114LABBeldarday1736.00736.00
0128LABMateday2.65816.002,162.40
0001MACHHire charges of Coaltar Boiler 900 to 1400 litresday0.5900.00450.00
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.753,350.002,512.50
9999MATMisc. items as spray nozzle, joint paper, coconut oil, country soap etcL.S.4292.27973.83
BUILD-UP TO RATE
TOTAL
1,56,924.43
Add 1 % Water charges on “W”
+1,569.24
TOTAL
1,58,493.67
Add GST on “X” (multiplying factor 0.2127)
+33,711.60
TOTAL
1,92,205.27
Add 15% CPOH on “Y”
+28,830.79
TOTAL
2,21,036.06
Add Cess @ 1% on “Z”
+2,210.36
Cost for 300 Sqm.
2,23,246.42
Cost per sqm.
744.15
SAY
₹744.15
D-02/SOURCEPRINTED PAGE 1193
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1193

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1193. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate