CPWD Analysis of Rates · Road Work

2.5 cm premix carpet surfacing with 3 cum of stone chippings 10 mm nominal size per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen contents) complying with IS : 8887, using 96 kg per cum of chippings of road surface, including consolidation with road roller etc complete

Item number
16.35
Analysis basis
Details of cost for 100 sqm.
Priced inputs
8
Derived rate
252.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.35 2.5 cm premix carpet surfacing with 3 cum of stone chippings 10 mm nominal size per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen contents) complying with IS : 8887, using 96 kg per cum of chippings of road surface, including consolidation with road roller etc complete — is derived from 8 priced inputs for 100 sqm and works out to ₹252.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bitumen emulsion M.S. @ 96kg per cum. of
  • aggregate
  • 96x3 = 288 kg = 0.288 t
  • @ 3.00 cum. per 100 sqm
  • (a) For mixing and spreading premix
  • aggregate :
  • (b) Consolidation Charges
CodeInputUnitQuantityRate (INR)Amount (INR)
7742Bitumen emulsion medium setting (M.S.) conforming to IS : 8887-1995Bitumen emulsion medium setting (M.S.) conforming to IS : 8887Materialtonne0.28833,530.009,656.64
2911Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterialcum31,400.004,200.00
0130MistryLabourday0.19897.00170.43
0114BeldarLabourday4.1736.003,017.60
0113ChowkidarLabourday0.27736.00198.72
0101BhistiLabourday0.11816.0089.76
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.113,350.00368.50
9999SundriesMaterialL.S.9.492.2721.54
TOTAL
17,723.19
Add 1 % Water charges on “W”
177.23
TOTAL
17,900.42
Add GST on “X” (multiplying factor 0.2127)
3,807.42
TOTAL
21,707.84
Add 15% CPOH on “Y”
3,256.18
TOTAL
24,964.02
Add Cess @ 1% on “Z”
249.64
Cost for 100 sqm.
25,213.66
Cost per Sqm.
252.14
Say
252.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1190. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.