2 cm premix carpet surfacing with 2.4 cum of stone chippings 11.2 mm nominal size per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen content) complying with IS : 8887, using 96 kg per cum of chippings, including consolidation with road roller of 6 to 9 tonne capacity etc. complete

Item number
16.34
Analysis basis
Details of cost for 100 sqm.
Priced inputs
9
Derived rate
208.90 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.34 2 cm premix carpet surfacing with 2.4 cum of stone chippings 11.2 mm nominal size per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen content) complying with IS : 8887, using 96 kg per cum of chippings, including consolidation with road roller of 6 to 9 tonne capacity etc. complete — is derived from 9 priced inputs for 100 sqm and works out to ₹208.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bitumen emulsion M.S. @ 96kg per cum. of
  • aggregate
  • 96x2.4=230kg =0.230t
  • @ 2.4cum. per 100 sqm
  • (a) For mixing and spreading premix
  • aggregate :
  • (b) Consolidation Charges
CodeInputUnitQuantityRate (INR)Amount (INR)
7742Bitumen emulsion medium setting (M.S.) conforming to IS : 8887-1995Bitumen emulsion medium setting (M.S.) conforming to IS : 8887Materialtonne0.2333,530.007,711.90
2911Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterialcum2.41,400.003,360.00
0130MistryLabourday0.19897.00170.43
0114BeldarLabourday3.54736.002,605.44
0113ChowkidarLabourday0.27736.00198.72
0101BhistiLabourday0.11816.0089.76
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.113,350.00368.50
0023Hot Bitumen mixer 0.5 cum i/c hand cartMachineryday0.043,950.00158.00
9999SundriesMaterialL.S.9.492.2721.54
TOTAL
14,684.29
Add 1 % Water charges on “W”
146.84
TOTAL
14,831.13
Add GST on “X” (multiplying factor 0.2127)
3,154.58
TOTAL
17,985.71
Add 15% CPOH on “Y”
2,697.86
TOTAL
20,683.57
Add Cess @ 1% on “Z”
206.84
Cost for 100 sqm.
20,890.41
Cost per Sqm.
208.90
Say
208.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1190. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.