2 cm premix carpet surfacing with 2.4 cum of stone chippings 11.2 mm nominal size per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen content) complying with IS : 8887, using 96 kg per cum of chippings, including consolidation with road roller of 6 to 9 tonne capacity etc. complete

Item number
16.34
Analysis basis
100 sqm
Priced inputs
9
Derived rate
₹208.90/ SQM
D-01/RATE ANALYSISITEM 16.34

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.34 (2 cm premix carpet surfacing with 2.4 cum of stone chippings 11.2 mm nominal size per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen content) complying with IS : 8887, using 96 kg per cum of chippings, including consolidation with road roller of 6 to 9 tonne capacity etc. complete) is derived from 9 priced inputs for 100 sqm and works out to ₹208.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Bitumen emulsion M.S. @ 96kg per cum. of
  • aggregate
  • 96x2.4=230kg =0.230t
  • @ 2.4cum. per 100 sqm
  • (a) For mixing and spreading premix
  • aggregate :
  • (b) Consolidation Charges
ANALYSIS OF RATES · ITEM 16.34DETAILS OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7742MATBitumen emulsion medium setting (M.S.) conforming to IS : 8887-1995Bitumen emulsion medium setting (M.S.) conforming to IS : 8887tonne0.2333,530.007,711.90
2911MATStone chippings/ screenings 10/ 11.2 mm nominal sizecum2.41,400.003,360.00
0130LABMistryday0.19897.00170.43
0114LABBeldarday3.54736.002,605.44
0113LABChowkidarday0.27736.00198.72
0101LABBhistiday0.11816.0089.76
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.113,350.00368.50
0023MACHHot Bitumen mixer 0.5 cum i/c hand cartday0.043,950.00158.00
9999MATSundriesL.S.9.492.2721.54
BUILD-UP TO RATE
TOTAL
14,684.29
Add 1 % Water charges on “W”
+146.84
TOTAL
14,831.13
Add GST on “X” (multiplying factor 0.2127)
+3,154.58
TOTAL
17,985.71
Add 15% CPOH on “Y”
+2,697.86
TOTAL
20,683.57
Add Cess @ 1% on “Z”
+206.84
Cost for 100 sqm.
20,890.41
Cost per Sqm.
208.90
SAY
₹208.90
D-02/SOURCEPRINTED PAGE 1190
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1190

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1190. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.