Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With rapid setting bitumen emulsion
- Item number
- 16.31.1.1
- Analysis basis
- 3500 sqm
- Priced inputs
- 6
- Derived rate
- ₹13.45/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.31.1.1 (Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With rapid setting bitumen emulsion On W.B.M / W.M.M. @ 0.4kg/sqm) is derived from 6 priced inputs for 3500 sqm and works out to ₹13.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7382 | MAT | Bitumen emulsion rapid setting (R.S.) conforming to IS : 8887-1995Bitumen emulsion rapid setting (R.S.) conforming to IS : 8887 | tonne | 1.4 | 19,893.00 | 27,850.20 |
| 0075 | MACH | Road sweeper (Mechamical Broom) @ 1250 sqm. Per hourRoad sweeper (Mechamical Broom) @ 1250 sqm per hour | hour | 2.8 | 500.00 | 1,400.00 |
| 0058 | MACH | Air compressor | hour | 2.8 | 250.00 | 700.00 |
| 0061 | MACH | Emulsion Pressure Distributor @ 1750 sqm per hourEmulsion Pressure Distributor of capacity 1750 sqm per hour | hour | 2 | 800.00 | 1,600.00 |
| 0128 | LAB | Mate | day | 0.08 | 816.00 | 65.28 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
- TOTAL
- 33,087.48
- Add 1 % Water charges on “W”
- +330.87
- TOTAL
- 33,418.35
- Add GST on “X” (multiplying factor 0.2127)
- +7,108.08
- TOTAL
- 40,526.43
- Add 15% CPOH on “Y”
- +6,078.96
- TOTAL
- 46,605.39
- Add Cess @ 1% on “Z”
- +466.05
- Cost for 3500 sqm.
- 47,071.44
- Cost per Sqm.
- 13.45
- SAY
- ₹13.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1179
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1179. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.