CPWD Analysis of Rates · Road Work

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With rapid setting bitumen emulsion

On bituminous surface @ 0.25kg/sqm

Item number
16.31.1.2
Analysis basis
Details of cost for 3500 sqm.
Priced inputs
6
Derived rate
9.20 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.31.1.2 Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With rapid setting bitumen emulsion On bituminous surface @ 0.25kg/sqm — is derived from 6 priced inputs for 3500 sqm and works out to ₹9.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7382Bitumen emulsion rapid setting (R.S.) conforming to IS : 8887-1995Bitumen emulsion rapid setting (R.S.) conforming to IS : 8887Materialtonne0.87519,893.0017,406.38
0075Road sweeper (Mechamical Broom) @ 1250 sqm. Per hourRoad sweeper (Mechamical Broom) @ 1250 sqm per hourMachineryhour2.8500.001,400.00
0058Air compressorMachineryhour2.8250.00700.00
0061Emulsion Pressure Distributor @ 1750 sqm per hourEmulsion Pressure Distributor of capacity 1750 sqm per hourMachineryhour2800.001,600.00
0128MateLabourday0.08816.0065.28
0114BeldarLabourday2736.001,472.00
TOTAL
22,643.66
Add 1 % Water charges on “W”
226.44
TOTAL
22,870.10
Add GST on “X” (multiplying factor 0.2127)
4,864.47
TOTAL
27,734.57
Add 15% CPOH on “Y”
4,160.19
TOTAL
31,894.76
Add Cess @ 1% on “Z”
318.95
Cost for 3500 sqm.
32,213.71
Cost per Sqm.
9.20
Say
9.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1180. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.