CPWD Analysis of Rates · Road Work
Providing and applying tack coat using hot straight run bitumen of grade VG - 10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications
On bituminous surface @ 0.50 Kg / sqm
- Item number
- 16.30.2
- Analysis basis
- Details of cost for 100 sqm.
- Priced inputs
- 11
- Derived rate
- ₹48.20 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.30.2 — Providing and applying tack coat using hot straight run bitumen of grade VG - 10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications : On bituminous surface @ 0.50 Kg / sqm — is derived from 11 priced inputs for 100 sqm and works out to ₹48.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- (with thick wire)
- (a) For cleaning :
- (b) For heating bitumen:
- (c) For applying tack coat:
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2916 | Paving Asphalt VG -10 of approved qualityPaving Asphalt VG 10 of approved qualityMaterial | tonne | 0.05 | 33,530.00 | 1,676.50 |
| 0370 | Coal (steam)Material | quintal | 0.1 | 500.00 | 50.00 |
| 0364 | Wire brushMaterial | each | 0.05 | 25.00 | 1.25 |
| 0365 | Soft brushMaterial | each | 0.12 | 25.00 | 3.00 |
| 9999 | Gunny bagsMaterial | L.S. | 7.8 | 2.27 | 17.71 |
| 0007 | Hire charges of Coaltar SprayerMachinery | day | 0.03 | 400.00 | 12.00 |
| 9999 | SundriesMaterial | L.S. | 7.8 | 2.27 | 17.71 |
| 0128 | MateLabour | day | 0.06 | 816.00 | 48.96 |
| 0114 | BeldarLabour | day | 1.46 | 736.00 | 1,074.56 |
| 0114 | BeldarLabour | day | 0.19 | 736.00 | 139.84 |
| 0114 | BeldarLabour | day | 0.47 | 736.00 | 345.92 |
- TOTAL
- 3,387.45
- Add 1 % Water charges on “W”
- 33.87
- TOTAL
- 3,421.32
- Add GST on “X” (multiplying factor 0.2127)
- 727.71
- TOTAL
- 4,149.03
- Add 15% CPOH on “Y”
- 622.35
- TOTAL
- 4,771.38
- Add Cess @ 1% on “Z”
- 47.71
- Cost for 100 sqm.
- 4,819.09
- Cost per Sqm.
- 48.19
- Say
- 48.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1178. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works