Skip to main content
R/DAR 2023

Supplying and stacking at site

53 mm to 22.4 mm size stone aggregate
Item number
16.3.3
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹1,842.30/ CUM
D-01/RATE ANALYSISITEM 16.3.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.3 (Supplying and stacking at site 53 mm to 22.4 mm size stone aggregate) is derived from 3 priced inputs for 1 cum and works out to ₹1,842.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 16.3.3DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0291MATStone Aggregate (Single size) : 63 mm nominal sizecum0.051,100.0055.00
0292MATStone Aggregate (Single size) : 50 mm nominal sizecum0.31,100.00330.00
0293MATStone Aggregate (Single size) : 40 mm nominal sizecum0.651,400.00910.00
BUILD-UP TO RATE
TOTAL
1,295.00
Add 1 % Water charges on "W"
+12.95
TOTAL
1,307.95
Add GST on "X" (multiplying factor 0.2127)
+278.20
TOTAL
1,586.15
Add 15% CPOH on "Y"
+237.92
TOTAL
1,824.07
Add Cess @ 1% on "Z"
+18.24
Cost for 1 cum
1,842.31
SAY
₹1,842.30
D-02/SOURCEPRINTED PAGE 1147
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1147

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1147. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.