Supplying and stacking at site
- Item number
- 16.3.2
- Analysis basis
- 1 cum
- Priced inputs
- 3
- Derived rate
- ₹1,636.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.2 (Supplying and stacking at site 63 mm to 45 mm size stone aggregate) is derived from 3 priced inputs for 1 cum and works out to ₹1,636.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2902 | MAT | Stone Aggregate (Single size) : 80 mm nominal sizeStone Aggregate (Single size): 80 mm nominal size | cum | 0.1 | 1,600.00 | 160.00 |
| 0291 | MAT | Stone Aggregate (Single size) : 63 mm nominal size | cum | 0.65 | 1,100.00 | 715.00 |
| 0292 | MAT | Stone Aggregate (Single size) : 50 mm nominal size | cum | 0.25 | 1,100.00 | 275.00 |
- TOTAL
- 1,150.00
- Add 1 % Water charges on “W”
- +11.50
- TOTAL
- 1,161.50
- Add GST on “X” (multiplying factor 0.2127)
- +247.05
- TOTAL
- 1,408.55
- Add 15% CPOH on “Y”
- +211.28
- TOTAL
- 1,619.83
- Add Cess @ 1% on “Z”
- +16.20
- Cost for 1 cum
- 1,636.03
- SAY
- ₹1,636.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1146
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1146. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.