CPWD Analysis of Rates · Road Work
Supplying and stacking at site
90 mm to 45 mm size stone aggregate
- Item number
- 16.3.1
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 3
- Derived rate
- ₹2,098.40 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.1 — Supplying and stacking at site 90 mm to 45 mm size stone aggregate — is derived from 3 priced inputs for 1 cum and works out to ₹2,098.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2901 | Stone Aggregate (Single size) : 100 mm nominal sizeStone Aggregate (Single size): 100 mm nominal sizeMaterial | cum | 0.1 | 1,600.00 | 160.00 |
| 2902 | Stone Aggregate (Single size) : 80 mm nominal sizeStone Aggregate (Single size): 80 mm nominal sizeMaterial | cum | 0.65 | 1,600.00 | 1,040.00 |
| 0291 | Stone Aggregate (Single size) : 63 mm nominal sizeMaterial | cum | 0.25 | 1,100.00 | 275.00 |
- TOTAL
- 1,475.00
- Add 1 % Water charges on "W"
- 14.75
- TOTAL
- 1,489.75
- Add GST on "X" (multiplying factor 0.2127)
- 316.87
- TOTAL
- 1,806.62
- Add 15% CPOH on "Y"
- 270.99
- TOTAL
- 2,077.61
- Add Cess @ 1% on "Z"
- 20.78
- Cost for 1 cum
- 2,098.39
- Say
- 2,098.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1146. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.