Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density)

Item number
16.2
Priced inputs
4
Derived rate
₹24.85
D-01/RATE ANALYSISITEM 16.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.2 (Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density)) is derived from 4 priced inputs and works out to ₹24.85 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (Extra to item No.2.3 in Earth work)
  • Roller charges (one roller does 1860sqm. Of
  • consolidation per day of 8 hours and uses
  • 18 litres diesel)
ANALYSIS OF RATES · ITEM 16.2
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0101LABBhistiday0.17816.00138.72
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.0083,350.0026.80
0113LABChowkidarday0.008736.005.89
9999MATSundriesL.S.1.432.273.25
BUILD-UP TO RATE
TOTAL
174.66
Add 1 % Water charges on “W”
+1.75
TOTAL
176.41
Add GST on “X” (multiplying factor 0.2127)
+37.52
TOTAL
213.93
Add 15% CPOH on “Y”
+32.09
TOTAL
246.02
Add Cess @ 1% on “Z”
+2.46
Cost of 10 cum.
248.48
Cost per cum.
24.85
SAY
₹24.85
D-02/SOURCEPRINTED PAGE 1145
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1145

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1145. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.