Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density)

Item number
16.2
Priced inputs
4
Derived rate
24.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.2 Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density) — is derived from 4 priced inputs and works out to ₹24.85 after water charges, GST, CPOH and cess. The full build-up is below.

  • (Extra to item No.2.3 in Earth work)
  • Roller charges (one roller does 1860sqm. Of
  • consolidation per day of 8 hours and uses
  • 18 litres diesel)
CodeInputUnitQuantityRate (INR)Amount (INR)
0101BhistiLabourday0.17816.00138.72
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.0083,350.0026.80
0113ChowkidarLabourday0.008736.005.89
9999SundriesMaterialL.S.1.432.273.25
TOTAL
174.66
Add 1 % Water charges on “W”
1.75
TOTAL
176.41
Add GST on “X” (multiplying factor 0.2127)
37.52
TOTAL
213.93
Add 15% CPOH on “Y”
32.09
TOTAL
246.02
Add Cess @ 1% on “Z”
2.46
Cost of 10 cum.
248.48
Cost per cum.
24.85
Say
24.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1145. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.