R/DAR 2023

Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earthwith lead upto 50 metres

Item number
16.1
Analysis basis
Details of cost for 100sqm.
Priced inputs
9
Derived rate
₹218.90
D-01/RATE ANALYSISITEM 16.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.1 (Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earthwith lead upto 50 metres) is derived from 9 priced inputs and works out to ₹218.90 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (A) preparation of subgrade.
  • Earth work in excavation including dressing
  • etc. 100sqm.x22.5cm (average depth) =
  • 22.5cum.
  • (B) Conslidation of subgrade
  • Roller charges (one roller does 1860 sqm.
  • of conosolidation of sub - grade with road
  • roller of 8 to 12 tonne capacity including
  • making good the undulations etc. with
  • earth or quarry spoils etc. and rerolling the
  • subgrade
ANALYSIS OF RATES · ITEM 16.1DETAILS OF COST FOR 100SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0128LABMateday1.8816.001,468.80
0115LABCoolieday18736.0013,248.00
0114LABBeldarday0.27736.00198.72
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.0543,350.00180.90
0113LABChowkidarday0.054736.0039.74
9999MATSundriesL.S.6.762.2715.35
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.0543,350.00180.90
0113LABChowkidarday0.054736.0039.74
9999MATSundriesL.S.6.762.2715.35
BUILD-UP TO RATE
TOTAL
15,387.50
Add 1 % Water charges on “W”
+153.88
TOTAL
15,541.38
Add GST on “X” (multiplying factor 0.2127)
+3,305.65
TOTAL
18,847.03
Add 15% CPOH on “Y”
+2,827.05
TOTAL
21,674.08
Add Cess @ 1% on “Z”
+216.74
Cost for 100 sqm.
21,890.82
Cost per sqm.
218.91
SAY
₹218.90
D-02/SOURCEPRINTED PAGE 1145
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1145

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1145. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.