CPWD Analysis of Rates · Road Work

Surface dressing one coat on old surface with bitumen of specified grade at the rate of 1.22 kg/ sqm of surface area with 1.10 cum of stone chippings 11.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity etc. complete

Using bitumen emulsion (minimum 50% bitumen contentRS grade conforming to IS : 8887)

Item number
16.29.1
Analysis basis
Details of cost for 100 sqm.
Priced inputs
19
Derived rate
125.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.29.1 Surface dressing one coat on old surface with bitumen of specified grade at the rate of 1.22 kg/ sqm of surface area with 1.10 cum of stone chippings 11.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity etc. complete : Using bitumen emulsion (minimum 50% bitumen contentRS grade conforming to IS : 8887) — is derived from 19 priced inputs for 100 sqm and works out to ₹125.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bitumen emulsion @1.22 kg per Sqm. =122
  • kg. or 0.122 tonne
  • Stone chippings 11.2mm nominal size @
  • 1.10cum. per 100 sqm
  • Labour for cleaning the road surface,
  • heating and spraying bitumen and
  • aggregate :
  • (a) For cleaning :
  • (b) For Spraying bitumen emulsion:
  • (c) For screening and spreading aggregate :
  • (d) Consolidation Charges
  • (e) Misc:
  • Brushes etc. for cleaning
  • (with thick wire)
CodeInputUnitQuantityRate (INR)Amount (INR)
0310Bitumen emulsionMaterialtonne0.12233,850.004,129.70
2911Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterialcum1.11,400.001,540.00
0128MateLabourday0.06816.0048.96
0114BeldarLabourday0.49736.00360.64
0115CoolieLabourday0.97736.00713.92
0130MistryLabourday0.05897.0044.85
0138Sprayer (for bitumen, tar etc.)Labourday0.06816.0048.96
0114BeldarLabourday0.63736.00463.68
0128MateLabourday0.07816.0057.12
0114BeldarLabourday0.62736.00456.32
0115CoolieLabourday0.62736.00456.32
0113ChowkidarLabourday0.15736.00110.40
0101BhistiLabourday0.15816.00122.40
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.063,350.00201.00
0007Hire charges of Coaltar SprayerMachineryday0.06400.0024.00
0364Wire brushMaterialeach0.1125.002.75
0365Soft brushMaterialeach0.3225.008.00
9999Brooms and gunny bagsMaterialL.S.2.732.276.20
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
8,807.32
Add 1 % Water charges on “W”
88.07
TOTAL
8,895.39
Add GST on “X” (multiplying factor 0.2127)
1,892.05
TOTAL
10,787.44
Add 15% CPOH on “Y”
1,618.12
TOTAL
12,405.56
Add Cess @ 1% on “Z”
124.06
Cost for 100 sqm.
12,529.62
Cost per Sqm.
125.30
Say
125.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1177. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.