CPWD Analysis of Rates · Road Work
Surface dressing one coat on new surface with bitumen of specified grade at a rate of 1.95 kg/sqm of surface area with 1.5 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity , etc. complete
Using bitumen emulsion (minimum 50% bitumen contentRS grade conforming to IS : 8887)
- Item number
- 16.28.1
- Analysis basis
- Details of cost for 100 sqm.
- Priced inputs
- 19
- Derived rate
- ₹198.45 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.28.1 — Surface dressing one coat on new surface with bitumen of specified grade at a rate of 1.95 kg/sqm of surface area with 1.5 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity , etc. complete : Using bitumen emulsion (minimum 50% bitumen contentRS grade conforming to IS : 8887) — is derived from 19 priced inputs for 100 sqm and works out to ₹198.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- @1.50 cum. per 100 sqm. = 1.50cum
- Labour for cleaning the road surface,
- heating and spraying bitumen and
- aggregate :
- (a) For cleaning :
- (b) For Spraying bitumen emulsion :
- (c) For screening and spreading aggregate :
- (d) Consolidation Charges
- (e) Misc:
- Brushes etc. for cleaning
- (with thick wire)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0310 | Bitumen emulsionMaterial | tonne | 0.195 | 33,850.00 | 6,600.75 |
| 2910 | Stone chippings/ screenings 12.5/ 13.2 mm nominal sizeMaterial | cum | 1.5 | 1,400.00 | 2,100.00 |
| 0128 | MateLabour | day | 0.11 | 816.00 | 89.76 |
| 0114 | BeldarLabour | day | 1.4 | 736.00 | 1,030.40 |
| 0115 | CoolieLabour | day | 1.4 | 736.00 | 1,030.40 |
| 0130 | MistryLabour | day | 0.07 | 897.00 | 62.79 |
| 0138 | Sprayer (for bitumen, tar etc.)Labour | day | 0.1 | 816.00 | 81.60 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0128 | MateLabour | day | 0.11 | 816.00 | 89.76 |
| 0114 | BeldarLabour | day | 0.85 | 736.00 | 625.60 |
| 0115 | CoolieLabour | day | 0.85 | 736.00 | 625.60 |
| 0113 | ChowkidarLabour | day | 0.27 | 736.00 | 198.72 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonneMachinery | day | 0.11 | 3,350.00 | 368.50 |
| 0007 | Hire charges of Coaltar SprayerMachinery | day | 0.1 | 400.00 | 40.00 |
| 0364 | Wire brushMaterial | each | 0.11 | 25.00 | 2.75 |
| 0365 | Soft brushMaterial | each | 0.32 | 25.00 | 8.00 |
| 9999 | Brooms and gunny bagsMaterial | L.S. | 6.76 | 2.27 | 15.35 |
| 9999 | SundriesMaterial | L.S. | 9.49 | 2.27 | 21.54 |
- TOTAL
- 13,947.84
- Add 1 % Water charges on “W”
- 139.48
- TOTAL
- 14,087.32
- Add GST on “X” (multiplying factor 0.2127)
- 2,996.37
- TOTAL
- 17,083.69
- Add 15% CPOH on “Y”
- 2,562.55
- TOTAL
- 19,646.24
- Add Cess @ 1% on “Z”
- 196.46
- Cost for 100 sqm.
- 19,842.70
- Cost per Sqm.
- 198.43
- Say
- 198.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1175. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.