CPWD Analysis of Rates · Road Work

Surface dressing on old surface with hot bitumen of grade VG - 10 of approved quality using 1.95 kg of bitumen per sqm with 1.50 cum of stone chippings 11.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity, etc. complete

Item number
16.27
Analysis basis
Details of cost for 100 sqm.
Priced inputs
21
Derived rate
175.10 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.27 Surface dressing on old surface with hot bitumen of grade VG - 10 of approved quality using 1.95 kg of bitumen per sqm with 1.50 cum of stone chippings 11.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity, etc. complete — is derived from 21 priced inputs for 100 sqm and works out to ₹175.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bitumen 1.95kg./sqm.= 195kg. or 0.195t
  • @ 1.50cum. per 100 sqm.
  • Steam coal for heating bitumen @2 qunital
  • per tonne of bitumen
  • Labour for cleaning the road surface,
  • heating and spraying bitumen and
  • aggregate etc.
  • (a) For cleaning :
  • (b) For heating and spraying bitumen :
  • (c) For screening and spreading aggregate :
  • (d) Consolidation Charges
  • (e) Misc:
  • Brushes etc. for cleaning
  • (with thick wire)
CodeInputUnitQuantityRate (INR)Amount (INR)
0309Paving bitumen VG-10 of approved qualityPaving bitumen of grade VG-10 of approved qualityMaterialtonne0.19533,530.006,538.35
2911Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterialcum1.51,400.002,100.00
0370Coal (steam)Materialquintal0.39500.00195.00
0128MateLabourday0.06816.0048.96
0114BeldarLabourday0.49736.00360.64
0115CoolieLabourday0.97736.00713.92
0130MistryLabourday0.05897.0044.85
0138Sprayer (for bitumen, tar etc.)Labourday0.06816.0048.96
0114BeldarLabourday0.69736.00507.84
0128MateLabourday0.66816.00538.56
0114BeldarLabourday0.51736.00375.36
0115CoolieLabourday0.51736.00375.36
0113ChowkidarLabourday0.15736.00110.40
0101BhistiLabourday0.06816.0048.96
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.063,350.00201.00
0007Hire charges of Coaltar SprayerMachineryday0.06400.0024.00
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.06900.0054.00
0364Wire brushMaterialeach0.0525.001.25
0365Soft brushMaterialeach0.1225.003.00
9999Brooms and gunny bagsMaterialL.S.2.732.276.20
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
12,308.71
Add 1 % Water charges on “W”
123.09
TOTAL
12,431.80
Add GST on “X” (multiplying factor 0.2127)
2,644.24
TOTAL
15,076.04
Add 15% CPOH on “Y”
2,261.41
TOTAL
17,337.45
Add Cess @ 1% on “Z”
173.37
Cost for 100 sqm.
17,510.82
Cost per Sqm.
175.11
Say
175.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1174. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.