CPWD Analysis of Rates · Road Work

Surface dressing on new surface in two coats with bitumen of grade VG -10 of approved quality using 1.8 kg of bitumen per sqm with 1.5 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface for first coat and 1.1 kg. of bitumen per sqm with 1.00 cu. metre of st one chippings 11.2 mm nominal size per 100 sqm of road surface for second coat, including consolidation of each coat separately with road roller of 6 to 8 tonne capacity etc. complete

Item number
16.26
Analysis basis
Details of cost for 100 sqm.
Priced inputs
40
Derived rate
311.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.26 Surface dressing on new surface in two coats with bitumen of grade VG -10 of approved quality using 1.8 kg of bitumen per sqm with 1.5 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface for first coat and 1.1 kg. of bitumen per sqm with 1.00 cu. metre of st one chippings 11.2 mm nominal size per 100 sqm of road surface for second coat, including consolidation of each coat separately with road roller of 6 to 8 tonne capacity etc. complete — is derived from 40 priced inputs for 100 sqm and works out to ₹311.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bitumen S-90/A-90 @ 1.8kg/
  • sqm.=180kg.=0.18 tonne
  • Steam coal for heating bitumen @2 qunital
  • per tonne
  • Labour for cleaning the road surface,
  • heating and spraying bitumen and
  • aggregate
  • (a) For cleaning :
  • (b) For heating and spraying bitumen :
  • (c) For screening and spreading aggregate :
  • (d) Consolidation Charges
  • (e) Misc:
  • Second Coat
  • Bitumen S-90/A-90 @ 1.10kg per sqm =
  • 110kg.=0.11 tonne
  • Steam coal for heating bitumen @2 qunital
  • per tonne of bitumen
  • Labour for cleaning the road surface,
  • heating and spraying bitumen and
  • aggregate
  • (a) For cleaning and brushing loose chips:
  • (b) For heating and spraying bitumen :
  • (c) For screening and spreading aggregate :
  • (d) Consolidation Charges
  • (e) Misc:
  • (with thick wire)
CodeInputUnitQuantityRate (INR)Amount (INR)
0309Paving bitumen VG-10 of approved qualityPaving bitumen of grade VG-10 of approved qualityMaterialtonne0.1833,530.006,035.40
2910Stone chippings/ screenings 12.5/ 13.2 mm nominal sizeMaterialcum1.51,400.002,100.00
0370Coal (steam)Materialquintal0.36500.00180.00
0128MateLabourday0.11816.0089.76
0114BeldarLabourday1.4736.001,030.40
0115CoolieLabourday1.4736.001,030.40
0130MistryLabourday0.08897.0071.76
0138Sprayer (for bitumen, tar etc.)Labourday0.11816.0089.76
0114BeldarLabourday1.38736.001,015.68
0128MateLabourday0.27816.00220.32
0114BeldarLabourday0.85736.00625.60
0115CoolieLabourday0.85736.00625.60
0113ChowkidarLabourday0.11736.0080.96
0101BhistiLabourday0.11816.0089.76
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.113,350.00368.50
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.12900.00108.00
0007Hire charges of Coaltar SprayerMachineryday0.11400.0044.00
0364Wire brushMaterialeach0.1125.002.75
0365Soft brushMaterialeach0.3225.008.00
9999Brooms and gunny bagsMaterialL.S.6.762.2715.35
9999SundriesMaterialL.S.16.382.2737.18
0309Paving bitumen VG-10 of approved qualityPaving bitumen of grade VG-10 of approved qualityMaterialtonne0.1133,530.003,688.30
2911Stone chippings/ screenings 10/ 11.2 mm nominal sizeMaterialcum11,400.001,400.00
0370Coal (steam)Materialquintal0.22500.00110.00
0128MateLabourday0.06816.0048.96
0115CoolieLabourday0.97736.00713.92
0130MistryLabourday0.05897.0044.85
0138Sprayer (for bitumen, tar etc.)Labourday0.07816.0057.12
0114BeldarLabourday0.75736.00552.00
0128MateLabourday0.07816.0057.12
0114BeldarLabourday0.62736.00456.32
0115CoolieLabourday0.62736.00456.32
0113ChowkidarLabourday0.15736.00110.40
0101BhistiLabourday0.06816.0048.96
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.063,350.00201.00
0007Hire charges of Coaltar SprayerMachineryday0.07400.0028.00
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.06900.0054.00
0364Wire brushMaterialeach0.0325.000.75
0365Soft brushMaterialeach0.0925.002.25
9999SundriesMaterialL.S.9.492.2721.54
TOTAL
21,920.99
Add 1 % Water charges on “W”
219.21
TOTAL
22,140.20
Add GST on “X” (multiplying factor 0.2127)
4,709.22
TOTAL
26,849.42
Add 15% CPOH on “Y”
4,027.41
TOTAL
30,876.83
Add Cess @ 1% on “Z”
308.77
Cost for per 100 sqm.
31,185.60
Cost per 1 Sqm.
311.86
Say
311.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1172. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.