CPWD Analysis of Rates · Road Work

Surface dressing on new surface with paving bitumen of grade VG - 10 of approved quality using 2.25 kg of bitumen per sqm with 1.65 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity etc. complete:

Item number
16.25
Analysis basis
Details of cost for 100 sqm.
Priced inputs
21
Derived rate
225.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.25 Surface dressing on new surface with paving bitumen of grade VG - 10 of approved quality using 2.25 kg of bitumen per sqm with 1.65 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity etc. complete: — is derived from 21 priced inputs for 100 sqm and works out to ₹225.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bitumen S-90@2.25kg per sqm. =225 kg =
  • 0.225 tonne.
  • Stone aggregate 13.2mm nominal size @
  • 1.65cum. per 100sqm.
  • Steam coal for heating bitumen @2 quintal
  • per tonne of bitumen = 2x0.225=0.450q
  • Labour for cleaning the road surface,
  • heating and spraying bitumen and
  • aggregate
  • (a) For cleaning :
  • (b) For heating and spraying bitumen :
  • (c) For screening and spreading aggregate :
  • (d) Consolidation Charges
  • (e) Misc:
CodeInputUnitQuantityRate (INR)Amount (INR)
0309Paving bitumen VG-10 of approved qualityPaving bitumen of grade VG-10 of approved qualityMaterialtonne0.22533,530.007,544.25
2910Stone chippings/ screenings 12.5/ 13.2 mm nominal sizeMaterialcum1.651,400.002,310.00
0370Coal (steam)Materialquintal0.45500.00225.00
0128MateLabourday0.11816.0089.76
0114BeldarLabourday1.4736.001,030.40
0115CoolieLabourday1.4736.001,030.40
0130MistryLabourday0.08897.0071.76
0138Sprayer (for bitumen, tar etc.)Labourday0.11816.0089.76
0114BeldarLabourday0.93736.00684.48
0128MateLabourday0.11816.0089.76
0114BeldarLabourday0.93736.00684.48
0115CoolieLabourday1.55736.001,140.80
0113ChowkidarLabourday0.27736.00198.72
0101BhistiLabourday0.11816.0089.76
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.113,350.00368.50
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.12900.00108.00
0007Hire charges of Coaltar SprayerMachineryday0.11400.0044.00
0364Wire brushMaterialeach0.1125.002.75
0365Soft brushMaterialeach0.3225.008.00
9999Brooms and gunny bagsMaterialL.S.6.762.2715.35
9999SundriesMaterialL.S.6.762.2715.35
TOTAL
15,841.28
Add 1 % Water charges on “W”
158.41
TOTAL
15,999.69
Add GST on “X” (multiplying factor 0.2127)
3,403.13
TOTAL
19,402.82
Add 15% CPOH on “Y”
2,910.42
TOTAL
22,313.24
Add Cess @ 1% on “Z”
223.13
Cost for 100 Sqm.
22,536.37
Cost per Sqm.
225.36
Say
225.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1171. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.