CPWD Analysis of Rates · Road Work
Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately
35x93.5x18 cm size
- Item number
- 16.24.3
- Analysis basis
- Details of cost for 10 Nos stone
- Priced inputs
- 21
- Derived rate
- ₹1,924.50 / Nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.3 — Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 35x93.5x18 cm size — is derived from 21 priced inputs for 10 Nos and works out to ₹1,924.50 each after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Cement concrete 1:1.5:3 (1 cement :1.5
- Coarse sand :3 graded stone aggregate
- 20mm nominal size)
- 0.35x0.18x0.835m = 0.0526 cum. +
- 0.37x0.20x0.10m = 0.0074 cum.
- = 0.060 cum.
- Volume for 10 nos. = 10x0.06 cum = 0.60
- cum
- (ii) Extra for laying cement concrete in RCC
- work
- (iii) M.S. reinforcement-0.60cum @48.06kg/
- cum. =28.8 kg.
- (iv) Centering and shuttering(0.35+2x0.18)x0.835 = 0.593 sqm
- (0.37+2x0.20)x0.10 = 0.077 sqm
- 2x0.35x0.18 = 0.126 sqm
- 2x0.37x0.01 = 0.007sqm
- 2x2x0.18x0.01 = 0.007sqm
- = 0.810 sqm
- Qty, for 10 Nos. Stone=10x0.810=8.10 sqm
- (v) 6mm cement plaster 1:3 (1 Cement :3
- fine sand)Qty. as per centering and shuttering =
- 0.810sqm
- 0.35x0.835 = 0.292sqm
- 0.37x0.10 =0.037sqm
- 2x0.37x0.01 =0.007sqm
- = 1.146 sqm Say 1.15sqm
- Qty, for 10 Nos. Stone=10x1.150=11.50
- sqm
- Labour for plaster
- (vi) Labour for fixing
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2Sub-analysis | cum | 0.6 | 8,340.85 | 5,004.51 | |
| 0114 | BeldarLabour | day | 0.06 | 736.00 | 44.16 |
| 0101 | BhistiLabour | day | 0.12 | 816.00 | 97.92 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.024 | 897.00 | 21.53 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.024 | 816.00 | 19.58 |
| 0128 | MateLabour | day | 0.024 | 816.00 | 19.58 |
| Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1Sub-analysis | kg | 28.8 | 107.10 | 3,084.48 | |
| Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysis | sqm | 8.1 | 392.15 | 3,176.42 | |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.42 | 5,156.00 | 2,165.52 |
| 0983 | Fine sand (zone IV)Material | cum | 0.09 | 980.00 | 88.20 |
| 0114 | BeldarLabour | day | 0.06 | 736.00 | 44.16 |
| 0101 | BhistiLabour | day | 0.006 | 816.00 | 4.90 |
| 9999 | Hire and running charges of mixerMaterial | L.S. | 2.6 | 2.27 | 5.90 |
| 9999 | SundriesMaterial | L.S. | 1.3 | 2.27 | 2.95 |
| 0155 | Mason (average)Labour | day | 0.58 | 857.00 | 497.06 |
| 0115 | CoolieLabour | day | 0.86 | 736.00 | 632.96 |
| 0101 | BhistiLabour | day | 1.05 | 816.00 | 856.80 |
| 9999 | Extra for removing burrMaterial | L.S. | 15.6 | 2.27 | 35.41 |
| 9999 | Scaffolding, sundries etc.Material | L.S. | 13 | 2.27 | 29.51 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 9977 | Carriage to siteMaterial | L.S. | 135.2 | 2.27 | 306.90 |
- TOTAL
- 16,874.45
- Add 1 % Water charges on “W-A”
- 56.09
- TOTAL
- 16,930.54
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,204.97
- TOTAL
- 18,135.51
- Add 15% CPOH on “Y-A”
- 1,030.52
- TOTAL
- 19,166.03
- Add Cess @ 1% on “Z-A”
- 79.01
- Cost for 10 Nos. stone
- 19,245.04
- Cost per stone
- 1,924.50
- Say
- 1,924.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1170. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.