Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately

35x93.5x18 cm size

Item number
16.24.3
Analysis basis
Details of cost for 10 Nos stone
Priced inputs
21
Derived rate
1,924.50 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.3 Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 35x93.5x18 cm size — is derived from 21 priced inputs for 10 Nos and works out to ₹1,924.50 each after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) Cement concrete 1:1.5:3 (1 cement :1.5
  • Coarse sand :3 graded stone aggregate
  • 20mm nominal size)
  • 0.35x0.18x0.835m = 0.0526 cum. +
  • 0.37x0.20x0.10m = 0.0074 cum.
  • = 0.060 cum.
  • Volume for 10 nos. = 10x0.06 cum = 0.60
  • cum
  • (ii) Extra for laying cement concrete in RCC
  • work
  • (iii) M.S. reinforcement-0.60cum @48.06kg/
  • cum. =28.8 kg.
  • (iv) Centering and shuttering(0.35+2x0.18)x0.835 = 0.593 sqm
  • (0.37+2x0.20)x0.10 = 0.077 sqm
  • 2x0.35x0.18 = 0.126 sqm
  • 2x0.37x0.01 = 0.007sqm
  • 2x2x0.18x0.01 = 0.007sqm
  • = 0.810 sqm
  • Qty, for 10 Nos. Stone=10x0.810=8.10 sqm
  • (v) 6mm cement plaster 1:3 (1 Cement :3
  • fine sand)Qty. as per centering and shuttering =
  • 0.810sqm
  • 0.35x0.835 = 0.292sqm
  • 0.37x0.10 =0.037sqm
  • 2x0.37x0.01 =0.007sqm
  • = 1.146 sqm Say 1.15sqm
  • Qty, for 10 Nos. Stone=10x1.150=11.50
  • sqm
  • Labour for plaster
  • (vi) Labour for fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2Sub-analysiscum0.68,340.855,004.51
0114BeldarLabourday0.06736.0044.16
0101BhistiLabourday0.12816.0097.92
0123Mason 1st classMason 1st classLabourday0.024897.0021.53
0124Mason 2nd classMason 2nd classLabourday0.024816.0019.58
0128MateLabourday0.024816.0019.58
Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1Sub-analysiskg28.8107.103,084.48
Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysissqm8.1392.153,176.42
0367Portland Cement (OPC-43 grade)Materialtonne0.425,156.002,165.52
0983Fine sand (zone IV)Materialcum0.09980.0088.20
0114BeldarLabourday0.06736.0044.16
0101BhistiLabourday0.006816.004.90
9999Hire and running charges of mixerMaterialL.S.2.62.275.90
9999SundriesMaterialL.S.1.32.272.95
0155Mason (average)Labourday0.58857.00497.06
0115CoolieLabourday0.86736.00632.96
0101BhistiLabourday1.05816.00856.80
9999Extra for removing burrMaterialL.S.15.62.2735.41
9999Scaffolding, sundries etc.MaterialL.S.132.2729.51
0114BeldarLabourday1736.00736.00
9977Carriage to siteMaterialL.S.135.22.27306.90
TOTAL
16,874.45
Add 1 % Water charges on “W-A”
56.09
TOTAL
16,930.54
Add GST on “X-A” (multiplying factor 0.2127)
1,204.97
TOTAL
18,135.51
Add 15% CPOH on “Y-A”
1,030.52
TOTAL
19,166.03
Add Cess @ 1% on “Z-A”
79.01
Cost for 10 Nos. stone
19,245.04
Cost per stone
1,924.50
Say
1,924.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1170. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.