Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately
- Item number
- 16.24.2
- Analysis basis
- one stone
- Priced inputs
- 21
- Derived rate
- ₹5,170.25/ ONE STONE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.2 (Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 50x152.5x25 cm size) is derived from 21 priced inputs for one stone and works out to ₹5,170.25 per one stone after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Cement concrete 1:1.5:3 (1 cement :1.5
- Coarse sand :3 graded stone aggregate
- 20mm nominal size)
- 0.50x0.25x1.145m = 0.143cum. +
- 0.52x0.27x0.13m = 0.018cum. +
- 1/2x22/7x(0.25)²x0.25m = 0.025cum.
- = 0.186 cum.
- (ii) Extra for laying cement concrete in RCC
- work
- (iii) M.S. reinforcement0.19cum @48.06kg/cum. =9.131kg.
- (iv) Centering and shuttering(0.50+2x0.25)x1.145 = 1.145 sqm
- 1/2x(0.25)²x3.142 = 0.098
- 3.142(0.25)x(0.25) =0.196
- (0.52+2x0.27)x0.13 =0.138
- 2x0.52x0.01 =0.10
- 2x2x0.25x0.01 =0.010
- 1x0.50x0.25 =0.125
- =1.722sqm. Say 1.72 sqm
- (v) 6mm cement plaster 1:3 (1 Cement : 3
- fine sand)Qty. as per centering and shuttering
- = 1.722sqm. +
- 0.50x1.145 = 0.572 +
- 0.52x0.13 = 0.068sqm. +
- 1/2x(0.25)²x3.142 = 0.098 +
- 2x0.52x001 = 0.010
- = 2.470sqm Sq. 2.47 sqm.
- Labour for plaster
- (vi) Labour for fixing
- Say 0.19cum.
- Say 9.13 kg.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2 | cum | 0.19 | 8,340.85 | 1,584.76 | |
| 0114 | LAB | Beldar | day | 0.019 | 736.00 | 13.98 |
| 0101 | LAB | Bhisti | day | 0.038 | 816.00 | 31.01 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.008 | 897.00 | 7.18 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.008 | 816.00 | 6.53 |
| 0128 | LAB | Mate | day | 0.008 | 816.00 | 6.53 |
| SUB | Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1 | kg | 9.13 | 107.10 | 977.82 | |
| SUB | Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1 | sqm | 1.72 | 392.15 | 674.50 | |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.09 | 5,156.00 | 464.04 |
| 0983 | MAT | Fine sand (zone IV) | cum | 0.2 | 980.00 | 196.00 |
| 0114 | LAB | Beldar | day | 0.013 | 736.00 | 9.57 |
| 0101 | LAB | Bhisti | day | 0.001 | 816.00 | 0.82 |
| 9999 | MAT | Hire and running charges of mixer | L.S. | 0.52 | 2.27 | 1.18 |
| 9999 | MAT | Sundries | L.S. | 0.26 | 2.27 | 0.59 |
| 0155 | LAB | Mason (average) | day | 0.126 | 857.00 | 107.98 |
| 0115 | LAB | Coolie | day | 0.185 | 736.00 | 136.16 |
| 0101 | LAB | Bhisti | day | 0.227 | 816.00 | 185.23 |
| 9999 | MAT | Extra for removing burr | L.S. | 3.38 | 2.27 | 7.67 |
| 9999 | MAT | Scaffolding, sundries etc. | L.S. | 2.86 | 2.27 | 6.49 |
| 0114 | LAB | Beldar | day | 0.2 | 736.00 | 147.20 |
| 9977 | MAT | Carriage to site | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 4,595.93
- Add 1 % Water charges on “W-A”
- +13.59
- TOTAL
- 4,609.52
- Add GST on “X-A” (multiplying factor 0.2127)
- +291.92
- TOTAL
- 4,901.44
- Add 15% CPOH on “Y-A”
- +249.65
- TOTAL
- 5,151.09
- Add Cess @ 1% on “Z-A”
- +19.14
- Cost per stone
- 5,170.23
- SAY
- ₹5,170.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1168
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1168. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.