CPWD Analysis of Rates · Road Work

Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately

50x152.5x25 cm size

Item number
16.24.2
Analysis basis
Details of cost for one stone
Priced inputs
21
Derived rate
5,170.25 / one stone

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.2 Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 50x152.5x25 cm size — is derived from 21 priced inputs for one stone and works out to ₹5,170.25 per one stone after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) Cement concrete 1:1.5:3 (1 cement :1.5
  • Coarse sand :3 graded stone aggregate
  • 20mm nominal size)
  • 0.50x0.25x1.145m = 0.143cum. +
  • 0.52x0.27x0.13m = 0.018cum. +
  • 1/2x22/7x(0.25)²x0.25m = 0.025cum.
  • = 0.186 cum.
  • (ii) Extra for laying cement concrete in RCC
  • work
  • (iii) M.S. reinforcement0.19cum @48.06kg/cum. =9.131kg.
  • (iv) Centering and shuttering(0.50+2x0.25)x1.145 = 1.145 sqm
  • 1/2x(0.25)²x3.142 = 0.098
  • 3.142(0.25)x(0.25) =0.196
  • (0.52+2x0.27)x0.13 =0.138
  • 2x0.52x0.01 =0.10
  • 2x2x0.25x0.01 =0.010
  • 1x0.50x0.25 =0.125
  • =1.722sqm. Say 1.72 sqm
  • (v) 6mm cement plaster 1:3 (1 Cement : 3
  • fine sand)Qty. as per centering and shuttering
  • = 1.722sqm. +
  • 0.50x1.145 = 0.572 +
  • 0.52x0.13 = 0.068sqm. +
  • 1/2x(0.25)²x3.142 = 0.098 +
  • 2x0.52x001 = 0.010
  • = 2.470sqm Sq. 2.47 sqm.
  • Labour for plaster
  • (vi) Labour for fixing
  • Say 0.19cum.
  • Say 9.13 kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2Sub-analysiscum0.198,340.851,584.76
0114BeldarLabourday0.019736.0013.98
0101BhistiLabourday0.038816.0031.01
0123Mason 1st classMason 1st classLabourday0.008897.007.18
0124Mason 2nd classMason 2nd classLabourday0.008816.006.53
0128MateLabourday0.008816.006.53
Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1Sub-analysiskg9.13107.10977.82
Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysissqm1.72392.15674.50
0367Portland Cement (OPC-43 grade)Materialtonne0.095,156.00464.04
0983Fine sand (zone IV)Materialcum0.2980.00196.00
0114BeldarLabourday0.013736.009.57
0101BhistiLabourday0.001816.000.82
9999Hire and running charges of mixerMaterialL.S.0.522.271.18
9999SundriesMaterialL.S.0.262.270.59
0155Mason (average)Labourday0.126857.00107.98
0115CoolieLabourday0.185736.00136.16
0101BhistiLabourday0.227816.00185.23
9999Extra for removing burrMaterialL.S.3.382.277.67
9999Scaffolding, sundries etc.MaterialL.S.2.862.276.49
0114BeldarLabourday0.2736.00147.20
9977Carriage to siteMaterialL.S.13.522.2730.69
TOTAL
4,595.93
Add 1 % Water charges on “W-A”
13.59
TOTAL
4,609.52
Add GST on “X-A” (multiplying factor 0.2127)
291.92
TOTAL
4,901.44
Add 15% CPOH on “Y-A”
249.65
TOTAL
5,151.09
Add Cess @ 1% on “Z-A”
19.14
Cost per stone
5,170.23
Say
5,170.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1168. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.