CPWD Analysis of Rates · Road Work
Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately
50x152.5x25 cm size
- Item number
- 16.24.2
- Analysis basis
- Details of cost for one stone
- Priced inputs
- 21
- Derived rate
- ₹5,170.25 / one stone
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.2 — Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 50x152.5x25 cm size — is derived from 21 priced inputs for one stone and works out to ₹5,170.25 per one stone after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Cement concrete 1:1.5:3 (1 cement :1.5
- Coarse sand :3 graded stone aggregate
- 20mm nominal size)
- 0.50x0.25x1.145m = 0.143cum. +
- 0.52x0.27x0.13m = 0.018cum. +
- 1/2x22/7x(0.25)²x0.25m = 0.025cum.
- = 0.186 cum.
- (ii) Extra for laying cement concrete in RCC
- work
- (iii) M.S. reinforcement0.19cum @48.06kg/cum. =9.131kg.
- (iv) Centering and shuttering(0.50+2x0.25)x1.145 = 1.145 sqm
- 1/2x(0.25)²x3.142 = 0.098
- 3.142(0.25)x(0.25) =0.196
- (0.52+2x0.27)x0.13 =0.138
- 2x0.52x0.01 =0.10
- 2x2x0.25x0.01 =0.010
- 1x0.50x0.25 =0.125
- =1.722sqm. Say 1.72 sqm
- (v) 6mm cement plaster 1:3 (1 Cement : 3
- fine sand)Qty. as per centering and shuttering
- = 1.722sqm. +
- 0.50x1.145 = 0.572 +
- 0.52x0.13 = 0.068sqm. +
- 1/2x(0.25)²x3.142 = 0.098 +
- 2x0.52x001 = 0.010
- = 2.470sqm Sq. 2.47 sqm.
- Labour for plaster
- (vi) Labour for fixing
- Say 0.19cum.
- Say 9.13 kg.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2Sub-analysis | cum | 0.19 | 8,340.85 | 1,584.76 | |
| 0114 | BeldarLabour | day | 0.019 | 736.00 | 13.98 |
| 0101 | BhistiLabour | day | 0.038 | 816.00 | 31.01 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.008 | 897.00 | 7.18 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.008 | 816.00 | 6.53 |
| 0128 | MateLabour | day | 0.008 | 816.00 | 6.53 |
| Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1Sub-analysis | kg | 9.13 | 107.10 | 977.82 | |
| Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysis | sqm | 1.72 | 392.15 | 674.50 | |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.09 | 5,156.00 | 464.04 |
| 0983 | Fine sand (zone IV)Material | cum | 0.2 | 980.00 | 196.00 |
| 0114 | BeldarLabour | day | 0.013 | 736.00 | 9.57 |
| 0101 | BhistiLabour | day | 0.001 | 816.00 | 0.82 |
| 9999 | Hire and running charges of mixerMaterial | L.S. | 0.52 | 2.27 | 1.18 |
| 9999 | SundriesMaterial | L.S. | 0.26 | 2.27 | 0.59 |
| 0155 | Mason (average)Labour | day | 0.126 | 857.00 | 107.98 |
| 0115 | CoolieLabour | day | 0.185 | 736.00 | 136.16 |
| 0101 | BhistiLabour | day | 0.227 | 816.00 | 185.23 |
| 9999 | Extra for removing burrMaterial | L.S. | 3.38 | 2.27 | 7.67 |
| 9999 | Scaffolding, sundries etc.Material | L.S. | 2.86 | 2.27 | 6.49 |
| 0114 | BeldarLabour | day | 0.2 | 736.00 | 147.20 |
| 9977 | Carriage to siteMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 4,595.93
- Add 1 % Water charges on “W-A”
- 13.59
- TOTAL
- 4,609.52
- Add GST on “X-A” (multiplying factor 0.2127)
- 291.92
- TOTAL
- 4,901.44
- Add 15% CPOH on “Y-A”
- 249.65
- TOTAL
- 5,151.09
- Add Cess @ 1% on “Z-A”
- 19.14
- Cost per stone
- 5,170.23
- Say
- 5,170.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1168. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.