CPWD Analysis of Rates · Road Work

Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately

35x111x25 cm size

Item number
16.24.1
Analysis basis
Details of cost for 10 Nos. stone
Priced inputs
21
Derived rate
2,876.70 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.1 Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 35x111x25 cm size — is derived from 21 priced inputs for 10 Nos and works out to ₹2,876.70 each after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) Cement concrete 1:1.5:3 (1 cement :1.5
  • Coarse sand :3 graded stone aggregate
  • 20mm nominal size) in Kilometre stone
  • 0.35x0.25x0.835m = 0.073
  • 0.37x0.27x0.10m = 0.010
  • 1/2x22/7x(0.175)²x0.25m = 0.012
  • = 0.095cum Say 0.10cum
  • Volume for 10 nos. = 10x0.10 cum = 1 cum
  • (ii) Extra for laying cement concrete in RCC
  • work
  • (iii) M.S. reinforcement- 1cum @48.06kg/
  • cum. =48.06kg. Say 48.1kg.
  • (iv) Centering and shuttering(0.35+2x0.25)x0.835 = 0.710 sqm
  • 0.35x0.25 = 0.088sqm
  • (0.37+2x0.27)x0.10 = 0.091sqm
  • 2x0.37x0.01 = 0.007 sqm
  • 2x2x0.25x0.1 = 0.010sqm
  • 1/2x3.142/4x(0.35)² = 0.048sqm
  • 1/2x0.35x0.25x3.142 = 0.138sqm.
  • = 1.092sqm. Say 1.09 sqm, qty for 10 nos
  • stone = 10x1.09 = 10.9 sqm
  • (v) 6mm cement plaster 1:3 (1 Cement : 3
  • fine sand)Qty. as per centering and shuttering =
  • 1.092sqm
  • 0.35x0.835 = 0.292sqm
  • 0.37x0.10 = 0.037sqm
  • 1/2x3.142/4x(0.35)²= 0.048sqm
  • 2x0.37x0.01 = 0.007 sqm
  • = 1.476 sqm Say 1.48 sqm, Qty for 10
  • stone = 10x1.48 sqm = 14.8 sqm
  • Labour for plaster
  • (vi) Labour for fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2Sub-analysiscum18,340.858,340.85
0114BeldarLabourday0.1736.0073.60
0101BhistiLabourday0.2816.00163.20
0123Mason 1st classMason 1st classLabourday0.04897.0035.88
0124Mason 2nd classMason 2nd classLabourday0.04816.0032.64
0128MateLabourday0.04816.0032.64
Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1Sub-analysiskg48.1107.105,151.51
Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysissqm10.9392.154,274.44
0367Portland Cement (OPC-43 grade)Materialtonne0.545,156.002,784.24
0983Fine sand (zone IV)Materialcum0.11980.00107.80
0114BeldarLabourday0.08736.0058.88
0101BhistiLabourday0.007816.005.71
9999Hire and running charges of mixerMaterialL.S.0.32.270.68
9999SundriesMaterialL.S.1.32.272.95
0155Mason (average)Labourday0.75857.00642.75
0115CoolieLabourday1.11736.00816.96
0101BhistiLabourday1.36816.001,109.76
9999Extra for removing burrMaterialL.S.19.52.2744.27
9999Scaffolding, sundries etc.MaterialL.S.18.22.2741.31
0114BeldarLabourday2736.001,472.00
9977Carriage to siteMaterialL.S.135.22.27306.90
TOTAL
25,498.97
Add 1 % Water charges on “W-A”
77.32
TOTAL
25,576.29
Add GST on “X-A” (multiplying factor 0.2127)
1,661.08
TOTAL
27,237.37
Add 15% CPOH on “Y-A”
1,420.59
TOTAL
28,657.96
Add Cess @ 1% on “Z-A”
108.91
Cost for 10 Nos. stone
28,766.87
Cost per stone
2,876.69
Say
2,876.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1167. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.