Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately

35x111x25 cm size
Item number
16.24.1
Analysis basis
10 Nos
Priced inputs
21
Derived rate
₹2,876.70/ NOS
D-01/RATE ANALYSISITEM 16.24.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.24.1 (Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) kilometre stone as per standard design, including finishing smooth in 1:3 cement mortar (1 cement : 3 fine sand) but excluding the cost of earth work, concrete in foundation, painting and lettering etc. which shall be paid for separately 35x111x25 cm size) is derived from 21 priced inputs for 10 Nos and works out to ₹2,876.70 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) Cement concrete 1:1.5:3 (1 cement :1.5
  • Coarse sand :3 graded stone aggregate
  • 20mm nominal size) in Kilometre stone
  • 0.35x0.25x0.835m = 0.073
  • 0.37x0.27x0.10m = 0.010
  • 1/2x22/7x(0.175)²x0.25m = 0.012
  • = 0.095cum Say 0.10cum
  • Volume for 10 nos. = 10x0.10 cum = 1 cum
  • (ii) Extra for laying cement concrete in RCC
  • work
  • (iii) M.S. reinforcement- 1cum @48.06kg/
  • cum. =48.06kg. Say 48.1kg.
  • (iv) Centering and shuttering(0.35+2x0.25)x0.835 = 0.710 sqm
  • 0.35x0.25 = 0.088sqm
  • (0.37+2x0.27)x0.10 = 0.091sqm
  • 2x0.37x0.01 = 0.007 sqm
  • 2x2x0.25x0.1 = 0.010sqm
  • 1/2x3.142/4x(0.35)² = 0.048sqm
  • 1/2x0.35x0.25x3.142 = 0.138sqm.
  • = 1.092sqm. Say 1.09 sqm, qty for 10 nos
  • stone = 10x1.09 = 10.9 sqm
  • (v) 6mm cement plaster 1:3 (1 Cement : 3
  • fine sand)Qty. as per centering and shuttering =
  • 1.092sqm
  • 0.35x0.835 = 0.292sqm
  • 0.37x0.10 = 0.037sqm
  • 1/2x3.142/4x(0.35)²= 0.048sqm
  • 2x0.37x0.01 = 0.007 sqm
  • = 1.476 sqm Say 1.48 sqm, Qty for 10
  • stone = 10x1.48 sqm = 14.8 sqm
  • Labour for plaster
  • (vi) Labour for fixing
ANALYSIS OF RATES · ITEM 16.24.1DETAILS OF COST FOR 10 NOS. STONE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2cum18,340.858,340.85
0114LABBeldarday0.1736.0073.60
0101LABBhistiday0.2816.00163.20
0123LABMason 1st classMason 1st classday0.04897.0035.88
0124LABMason 2nd classMason 2nd classday0.04816.0032.64
0128LABMateday0.04816.0032.64
SUBRate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1kg48.1107.105,151.51
SUBRate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1sqm10.9392.154,274.44
0367MATPortland Cement (OPC-43 grade)tonne0.545,156.002,784.24
0983MATFine sand (zone IV)cum0.11980.00107.80
0114LABBeldarday0.08736.0058.88
0101LABBhistiday0.007816.005.71
9999MATHire and running charges of mixerL.S.0.32.270.68
9999MATSundriesL.S.1.32.272.95
0155LABMason (average)day0.75857.00642.75
0115LABCoolieday1.11736.00816.96
0101LABBhistiday1.36816.001,109.76
9999MATExtra for removing burrL.S.19.52.2744.27
9999MATScaffolding, sundries etc.L.S.18.22.2741.31
0114LABBeldarday2736.001,472.00
9977MATCarriage to siteL.S.135.22.27306.90
BUILD-UP TO RATE
TOTAL
25,498.97
Add 1 % Water charges on “W-A”
+77.32
TOTAL
25,576.29
Add GST on “X-A” (multiplying factor 0.2127)
+1,661.08
TOTAL
27,237.37
Add 15% CPOH on “Y-A”
+1,420.59
TOTAL
28,657.96
Add Cess @ 1% on “Z-A”
+108.91
Cost for 10 Nos. stone
28,766.87
Cost per stone
2,876.69
SAY
₹2,876.70
D-02/SOURCEPRINTED PAGE 1167
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1167

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1167. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.