Providing and fixing 15 cm dia at top, 20 cm at bottom and 90 cm high precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) boundary stone as per standard design, including finishing smooth with cement mortar 1:3 (1 cement : 3 fine sand) (cost of excavation, refilling and concreting to be paid for separately)
- Item number
- 16.23
- Analysis basis
- 10 Nos
- Priced inputs
- 21
- Derived rate
- ₹852.40/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.23 (Providing and fixing 15 cm dia at top, 20 cm at bottom and 90 cm high precast reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) boundary stone as per standard design, including finishing smooth with cement mortar 1:3 (1 cement : 3 fine sand) (cost of excavation, refilling and concreting to be paid for separately)) is derived from 21 priced inputs for 10 Nos and works out to ₹852.40 each after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Cement concrete 1:1½:3 (1 cement : 1½
- Coarse sand : 3 graded stone aggregate
- 20mm nominal size)
- Volume of frustum of cone:
- L/3 x [A1+A2+sqrt(A1A2)] = (0.825/3) x
- [0.095²+0.075² + sqrt(0.095 x 0.075²)]
- x3.142=0.01882 (A)
- Volume of hemi sphere:
- ½ x 4 /3 x PI x r³ = ½x(4/ 3)x(22/7)
- x0.075³=0.00100 (B)
- Total volume one Nos.= A+B = 0.01982 Say
- 0.02cum, Volume for 10 Nos. = 10x0.02=
- 0.2 cum
- (ii) Extra for laying cement concerte in RCC
- work
- (iii) M.S. reinforcement- 6mm dia. Bar
- 5.99 metre =10x 5.99x0.22 =13.2kg.
- (iv) Centering and shuttering1/2x3.142 (0.19+0.15)x0.825 =0.441 +
- 3.142/4(0.19)² =0.028 +
- 1/2x4x3.142(0.075)² = 0.035
- = 0.504 Say 0.50sqm
- Qty for 10 Nos. = 10x0.50 = 5.00 sqm
- (v) 6mm cement plaster 1:3 (1 Cement : 3
- fine sand)1/2x3.142 (0.19+0.15)x0.825 =0.44 +
- 3.142/4(0.19)² =0.028 +
- 1/2x4x3.142(0.075)² = 0.035
- = 0.504 Say 0.50sqm
- Qty for 10 Nos. = 10x0.50 = 5.00 sqm
- Labour for plaster
- (vi) Labour for fixing
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2 | cum | 0.2 | 8,340.85 | 1,668.17 | |
| 0114 | LAB | Beldar | day | 0.02 | 736.00 | 14.72 |
| 0101 | LAB | Bhisti | day | 0.04 | 816.00 | 32.64 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.008 | 897.00 | 7.18 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.008 | 816.00 | 6.53 |
| 0128 | LAB | Mate | day | 0.008 | 816.00 | 6.53 |
| SUB | Rate as per item no. 5.22.1 of SH : RCC workRate as per item 5.22.1 | kg | 13.2 | 107.10 | 1,413.72 | |
| SUB | Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1 | sqm | 5 | 392.15 | 1,960.75 | |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.018 | 5,156.00 | 92.81 |
| 0983 | MAT | Fine sand (zone IV) | cum | 0.385 | 980.00 | 377.30 |
| 0114 | LAB | Beldar | day | 0.027 | 736.00 | 19.87 |
| 0101 | LAB | Bhisti | day | 0.002 | 816.00 | 1.63 |
| 9999 | MAT | Hire and running charges of mixer | L.S. | 1 | 2.27 | 2.27 |
| 9999 | MAT | Sundries | L.S. | 0.5 | 2.27 | 1.14 |
| 0155 | LAB | Mason (average) | day | 0.26 | 857.00 | 222.82 |
| 0115 | LAB | Coolie | day | 0.38 | 736.00 | 279.68 |
| 0101 | LAB | Bhisti | day | 0.46 | 816.00 | 375.36 |
| 9999 | MAT | Extra for removing burr | L.S. | 6.8 | 2.27 | 15.44 |
| 9999 | MAT | Scaffolding, sundries etc. | L.S. | 6 | 2.27 | 13.62 |
| 0114 | LAB | Beldar | day | 1.2 | 736.00 | 883.20 |
| 9977 | MAT | Carriage to site | L.S. | 41.6 | 2.27 | 94.43 |
- TOTAL
- 7,489.81
- Add 1 % Water charges on “W-A”
- +24.47
- TOTAL
- 7,514.28
- Add GST on “X-A” (multiplying factor 0.2127)
- +525.72
- TOTAL
- 8,040.00
- Add 15% CPOH on “Y-A”
- +449.60
- TOTAL
- 8,489.60
- Add Cess @ 1% on “Z-A”
- +34.47
- Cost of 10 nos. stone
- 8,524.07
- Cost of each.
- 852.41
- SAY
- ₹852.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1165
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1165. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.