CPWD Analysis of Rates · Road Work
Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately)
- Item number
- 16.22
- Analysis basis
- Details of cost for one stone
- Priced inputs
- 3
- Derived rate
- ₹252.90 / one stone
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.22 — Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately) — is derived from 3 priced inputs for one stone and works out to ₹252.90 per one stone after water charges, GST, CPOH and cess. The full build-up is below.
- Labour for fixing
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1151 | Boundry stone top chisel dressed 15x15x90 cmBoundary stone top chisel dressed 15x15x90 cmMaterial | each | 1 | 80.00 | 80.00 |
| 0114 | BeldarLabour | day | 0.12 | 736.00 | 88.32 |
| 9977 | Carriage to siteMaterial | L.S. | 4.16 | 2.27 | 9.44 |
- TOTAL
- 177.76
- Add 1 % Water charges on “W”
- 1.78
- TOTAL
- 179.54
- Add GST on “X” (multiplying factor 0.2127)
- 38.19
- TOTAL
- 217.73
- Add 15% CPOH on “Y”
- 32.66
- TOTAL
- 250.39
- Add Cess @ 1% on “Z”
- 2.50
- Cost of each.
- 252.89
- Say
- 252.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1164. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.