Skip to main content

CPWD Analysis of Rates · Road Work

Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately)

Item number
16.22
Analysis basis
Details of cost for one stone
Priced inputs
3
Derived rate
252.90 / one stone

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.22 Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately) — is derived from 3 priced inputs for one stone and works out to ₹252.90 per one stone after water charges, GST, CPOH and cess. The full build-up is below.

  • Labour for fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
1151Boundry stone top chisel dressed 15x15x90 cmBoundary stone top chisel dressed 15x15x90 cmMaterialeach180.0080.00
0114BeldarLabourday0.12736.0088.32
9977Carriage to siteMaterialL.S.4.162.279.44
TOTAL
177.76
Add 1 % Water charges on “W”
1.78
TOTAL
179.54
Add GST on “X” (multiplying factor 0.2127)
38.19
TOTAL
217.73
Add 15% CPOH on “Y”
32.66
TOTAL
250.39
Add Cess @ 1% on “Z”
2.50
Cost of each.
252.89
Say
252.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1164. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works