Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately)
- Item number
- 16.22
- Analysis basis
- one stone
- Priced inputs
- 3
- Derived rate
- ₹252.90/ ONE STONE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.22 (Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately)) is derived from 3 priced inputs for one stone and works out to ₹252.90 per one stone after water charges, GST, CPOH and cess. The full build-up is below.
- Labour for fixing
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1151 | MAT | Boundry stone top chisel dressed 15x15x90 cmBoundary stone top chisel dressed 15x15x90 cm | each | 1 | 80.00 | 80.00 |
| 0114 | LAB | Beldar | day | 0.12 | 736.00 | 88.32 |
| 9977 | MAT | Carriage to site | L.S. | 4.16 | 2.27 | 9.44 |
- TOTAL
- 177.76
- Add 1 % Water charges on “W”
- +1.78
- TOTAL
- 179.54
- Add GST on “X” (multiplying factor 0.2127)
- +38.19
- TOTAL
- 217.73
- Add 15% CPOH on “Y”
- +32.66
- TOTAL
- 250.39
- Add Cess @ 1% on “Z”
- +2.50
- Cost of each.
- 252.89
- SAY
- ₹252.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1164
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1164. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.