Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used
- Item number
- 16.17.1
- Analysis basis
- 30 m
- Priced inputs
- 8
- Derived rate
- ₹14.00/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.17.1 (Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per metre cost of total length of barbed wire used With G.I. barbed wire) is derived from 8 priced inputs for 30 m and works out to ₹14.00 per m after water charges, GST, CPOH and cess. The full build-up is below.
- length of barbed wire
- G.I. barbed wire
- 30x9 = 270m +
- 10x6.32 = 63m
- Total = 333m
- 333m @9.38kg/100m =31.24kg = 0.31q
- Labour for fixing costs in line, fixing and
- stretching wire
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1029 | MAT | Galvanised steel barbed wireGalvanised steel barbed wire of 9.8 kg /100metre | quintal | 0.31 | 5,500.00 | 1,705.00 |
| 9999 | MAT | G.I. staples or binding wire | L.S. | 49.4 | 2.27 | 112.14 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.12 | 897.00 | 107.64 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.12 | 816.00 | 97.92 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 0102 | LAB | Blacksmith 1st class | day | 0.5 | 897.00 | 448.50 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.5 | 816.00 | 408.00 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 3,277.89
- Add 1 % Water charges on “W”
- +32.78
- TOTAL
- 3,310.67
- Add GST on “X” (multiplying factor 0.2127)
- +704.18
- TOTAL
- 4,014.85
- Add 15% CPOH on “Y”
- +602.23
- TOTAL
- 4,617.08
- Add Cess @ 1% on “Z”
- +46.17
- Cost for 333m
- 4,663.25
- Cost per m
- 14.00
- SAY
- ₹14.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1161
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1161. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.