Supplying and fixing turn buckles and straining bolts for barbed wire fencing

Item number
16.16
Analysis basis
one set
Priced inputs
4
Derived rate
₹274.30/ ONE SET
D-01/RATE ANALYSISITEM 16.16

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.16 (Supplying and fixing turn buckles and straining bolts for barbed wire fencing) is derived from 4 priced inputs for one set and works out to ₹274.30 per one set after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Labour for fixing straining bolts and turn
  • buckles
ANALYSIS OF RATES · ITEM 16.16DETAILS OF COST FOR ONE SET
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1030MATGalvanised steel turn buckleseach125.0025.00
1028MATStraining boltseach180.0080.00
9977MATCarriage of turn buckles and straining boltsL.S.2.732.276.20
0103LABBlacksmith 2nd classday0.1816.0081.60
BUILD-UP TO RATE
TOTAL
192.80
Add 1 % Water charges on “W”
+1.93
TOTAL
194.73
Add GST on “X” (multiplying factor 0.2127)
+41.42
TOTAL
236.15
Add 15% CPOH on “Y”
+35.42
TOTAL
271.57
Add Cess @ 1% on “Z”
+2.72
Cost per set
274.29
SAY
₹274.30
D-02/SOURCEPRINTED PAGE 1160
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1160

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1160. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.