Welded steel wire fabric of required width having rectangular mesh painted with two or more coats of enamel paint of approved shade over a coat of primer (Priming & Painting to be paid for separately)
Item number
16.15.2
Analysis basis
27 sqm
Priced inputs
1
Derived rate
₹78.95/ SQM
D-01/RATE ANALYSISITEM 16.15.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.15.2 (Supplying at site : Welded steel wire fabric of required width having rectangular mesh painted with two or more coats of enamel paint of approved shade over a coat of primer (Priming & Painting to be paid for separately)) is derived from 1 priced inputs for 27 sqm and works out to ₹78.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Steel wire fabric 0.9m wide rectangular
  • mesh 75x25mm size weight not less than
  • 7.75kg/sqm. 30x0.9 = 27sqm
  • 7.75x27=209.25kg=0.209tonne
ANALYSIS OF RATES · ITEM 16.15.2DETAILS OF COST FOR 27 SQM (209.25 KG)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1021MATHard drawn steel wire fabricHard drawn steel wire fabric 75 x 25 mm mesh of weight not less than 7.75 kg/sqmsqm27430.0011,610.00
BUILD-UP TO RATE
TOTAL
11,610.00
Add 1 % Water charges on "W"
+116.10
TOTAL
11,726.10
Add GST on "X" (multiplying factor 0.2127)
+2,494.14
TOTAL
14,220.24
Add 15% CPOH on "Y"
+2,133.04
TOTAL
16,353.28
Add Cess @ 1% on "Z"
+163.53
Cost for 209.25 kg
16,516.81
Cost per kg.
78.93
SAY
₹78.95
D-02/SOURCEPRINTED PAGE 1160
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1160

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1160. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.