CPWD Analysis of Rates · Road Work
Supplying at site
R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5 coarsesand: 3 graded stone aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar nibs wherever required as per direction of Engineer-incharge (cost of earth works in excavation, concrete works in foundation to be paid separately)
- Item number
- 16.15.1
- Analysis basis
- Details of cost for 9.88 sqm.
- Priced inputs
- 21
- Derived rate
- ₹32,891.20 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.15.1 — Supplying at site : R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5 coarsesand: 3 graded stone aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar nibs wherever required as per direction of Engineer-incharge (cost of earth works in excavation, concrete works in foundation to be paid separately) — is derived from 21 priced inputs for 9.88 sqm and works out to ₹32,891.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cubical contents of one post
- Area bottom A1 = (15+12.5)/2
- x8.75+½x3.14 x(6.25)²
- =120.31+61.38=181.69sqcm.
- Area bottom A2 = (10+7.5)/2 x6.25+½x3.14
- x(3.75)² sqm
- = 54.68+22.08 = 76.76 sqcm.
- (A1A2)^½ = 118.10sqcm
- A1+A2+(A1A2))^½ = 0.03766 sqm
- Volume = (1.05)/3x0.03766 = 0.01316 cum
- =0.0132cum.
- Volume of lower and square portion
- (16.5x16.5x75) / 100³ = 0.0204cum.
- Total volume = 0.0132+0.0204 cum
- = 0.0336 cum.
- Qty. for 10 post
- = 0.0336x10 = 0.336cum.
- Cement concrete 1:1.5:3 (1 Cement : 1.5
- Coarse sand : 3 graded stone aggregate
- 12.5mm nominal size)
- Extra labour for laying cement concrete in
- RCC work
- M.S. Reinforcement
- 6mm dia. bars
- 10x4x1.88m = 75.20m+
- 10x9x0.50m =45.00m = 120.20m
- 120.20m@0.22kg/m =26.44kg.
- Centering and shuttering
- 6mm C.Plaster 1:2 (1 Cement : 2 fine sand)
- (0.072)/10x9.88 = 0.071
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2Sub-analysis | cum | 0.336 | 8,340.85 | 2,802.53 | |
| 0114 | BeldarLabour | day | 0.034 | 736.00 | 25.02 |
| 0101 | BhistiLabour | day | 0.067 | 816.00 | 54.67 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.013 | 897.00 | 11.66 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.013 | 816.00 | 10.61 |
| 0128 | MateLabour | day | 0.013 | 816.00 | 10.61 |
| Rate as per Item No.5.22.2 of SH: Reinforced cement concrete workRate as per item 5.22.2Sub-analysis | kg | 26.44 | 95.80 | 2,532.95 | |
| Rate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1Sub-analysis | sqm | 6.99 | 392.15 | 2,741.13 | |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.05 | 5,156.00 | 257.80 |
| 0983 | Fine sand (zone IV)Material | cum | 0.07 | 980.00 | 68.60 |
| 0114 | BeldarLabour | day | 0.05 | 736.00 | 36.80 |
| 0101 | BhistiLabour | day | 0.02 | 816.00 | 16.32 |
| 0155 | Mason (average)Labour | day | 0.64 | 857.00 | 548.48 |
| 0115 | CoolieLabour | day | 0.8 | 736.00 | 588.80 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
| 9999 | Hire and running charges of mixerMaterial | L.S. | 1.95 | 2.27 | 4.43 |
| 9999 | Extra for removing burr, cleaning with wire brushes, pock making with pointed tool etc. completeMaterial | L.S. | 13.26 | 2.27 | 30.10 |
| 9999 | Scaffolding and sundriesMaterial | L.S. | 11.57 | 2.27 | 26.26 |
| 9977 | Carriage of RCC postsMaterial | L.S. | 53.82 | 2.27 | 122.17 |
| 9999 | Wooden plugs or 6mm bar nibsMaterial | L.S. | 12.22 | 2.27 | 27.74 |
| 9999 | SundriesMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 10,167.69
- Add 1 % Water charges on “W-A”
- 20.91
- TOTAL
- 10,188.60
- Add GST on “X-A” (multiplying factor 0.2127)
- 449.22
- TOTAL
- 10,637.82
- Add 15% CPOH on “Y-A”
- 384.18
- TOTAL
- 11,022.00
- Add Cess @ 1% on “Z-A”
- 29.45
- Cost for 0.336 cum
- 11,051.45
- Cost for one cum
- 32,891.22
- Say
- 32,891.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1158. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.