Skip to main content
R/DAR 2023

Supplying at site

R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5 coarsesand: 3 graded stone aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar nibs wherever required as per direction of Engineer-incharge (cost of earth works in excavation, concrete works in foundation to be paid separately)
Item number
16.15.1
Analysis basis
9.88 sqm
Priced inputs
21
Derived rate
₹32,891.20/ SQM
D-01/RATE ANALYSISITEM 16.15.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.15.1 (Supplying at site : R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5 coarsesand: 3 graded stone aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar nibs wherever required as per direction of Engineer-incharge (cost of earth works in excavation, concrete works in foundation to be paid separately)) is derived from 21 priced inputs for 9.88 sqm and works out to ₹32,891.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cubical contents of one post
  • Area bottom A1 = (15+12.5)/2
  • x8.75+½x3.14 x(6.25)²
  • =120.31+61.38=181.69sqcm.
  • Area bottom A2 = (10+7.5)/2 x6.25+½x3.14
  • x(3.75)² sqm
  • = 54.68+22.08 = 76.76 sqcm.
  • (A1A2)^½ = 118.10sqcm
  • A1+A2+(A1A2))^½ = 0.03766 sqm
  • Volume = (1.05)/3x0.03766 = 0.01316 cum
  • =0.0132cum.
  • Volume of lower and square portion
  • (16.5x16.5x75) / 100³ = 0.0204cum.
  • Total volume = 0.0132+0.0204 cum
  • = 0.0336 cum.
  • Qty. for 10 post
  • = 0.0336x10 = 0.336cum.
  • Cement concrete 1:1.5:3 (1 Cement : 1.5
  • Coarse sand : 3 graded stone aggregate
  • 12.5mm nominal size)
  • Extra labour for laying cement concrete in
  • RCC work
  • M.S. Reinforcement
  • 6mm dia. bars
  • 10x4x1.88m = 75.20m+
  • 10x9x0.50m =45.00m = 120.20m
  • 120.20m@0.22kg/m =26.44kg.
  • Centering and shuttering
  • 6mm C.Plaster 1:2 (1 Cement : 2 fine sand)
  • (0.072)/10x9.88 = 0.071
ANALYSIS OF RATES · ITEM 16.15.1DETAILS OF COST FOR 9.88 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.1.2 of S.H. Concrete WorkRate as per item 4.1.2cum0.3368,340.852,802.53
0114LABBeldarday0.034736.0025.02
0101LABBhistiday0.067816.0054.67
0123LABMason 1st classMason 1st classday0.013897.0011.66
0124LABMason 2nd classMason 2nd classday0.013816.0010.61
0128LABMateday0.013816.0010.61
SUBRate as per Item No.5.22.2 of SH: Reinforced cement concrete workRate as per item 5.22.2kg26.4495.802,532.95
SUBRate as per item No.5.9.1 of SH : Reinforced cement concrete workRate as per item 5.9.1sqm6.99392.152,741.13
0367MATPortland Cement (OPC-43 grade)tonne0.055,156.00257.80
0983MATFine sand (zone IV)cum0.07980.0068.60
0114LABBeldarday0.05736.0036.80
0101LABBhistiday0.02816.0016.32
0155LABMason (average)day0.64857.00548.48
0115LABCoolieday0.8736.00588.80
0101LABBhistiday0.27816.00220.32
9999MATHire and running charges of mixerL.S.1.952.274.43
9999MATExtra for removing burr, cleaning with wire brushes, pock making with pointed tool etc. completeL.S.13.262.2730.10
9999MATScaffolding and sundriesL.S.11.572.2726.26
9977MATCarriage of RCC postsL.S.53.822.27122.17
9999MATWooden plugs or 6mm bar nibsL.S.12.222.2727.74
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
10,167.69
Add 1 % Water charges on “W-A”
+20.91
TOTAL
10,188.60
Add GST on “X-A” (multiplying factor 0.2127)
+449.22
TOTAL
10,637.82
Add 15% CPOH on “Y-A”
+384.18
TOTAL
11,022.00
Add Cess @ 1% on “Z-A”
+29.45
Cost for 0.336 cum
11,051.45
Cost for one cum
32,891.22
SAY
₹32,891.20
D-02/SOURCEPRINTED PAGE 1158
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1158

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1158. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.