Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required

Water bound macadam

Item number
16.13.2
Analysis basis
Details of cost for 0.90cum.
Priced inputs
11
Derived rate
3,078.05

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.13.2 Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required Water bound macadam — is derived from 11 priced inputs and works out to ₹3,078.05 after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider a road 6 metres wide and 0.6m.
  • lengthwise and 0.25m cm average depth
  • =0.90cum.
  • Supplying and stacking stone aggregate
  • 53mm to 24mm nominal size at site.
  • Supplying and stacking red bajri at site
  • Supplying and stacking moorum at site.
  • For cutting road and taking out soling and
  • metalling including sorting and screening.
  • For relaying soling stone 3.6x0.15=0.54cum.
  • For relaying road metal with extra quantity
  • and consolidation to 0.10m thickness
  • - 3.6x0.10=0.36cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 16.3.3 of SH: Road WorkRate as per item 16.3.3Sub-analysiscum0.091,842.30165.81
Rate as per Item Number 16.3.8 of SH: Road WorkRate as per item 16.3.8Sub-analysiscum0.0231,564.9035.99
Rate as per Item Number 16.3.10 of SH: Road WorkRate as per item 16.3.10Sub-analysiscum0.022768.2516.90
0114BeldarLabourday0.48736.00353.28
0115CoolieLabourday0.24736.00176.64
0114BeldarLabourday0.24736.00176.64
0115CoolieLabourday0.24736.00176.64
0114BeldarLabourday0.48736.00353.28
0115CoolieLabourday0.48736.00353.28
0101BhistiLabourday0.1816.0081.60
9999Barrier and chowkidar etc.MaterialL.S.53.822.27122.17
TOTAL
2,012.23
Add 1 % Water charges on “W-A”
17.94
TOTAL
2,030.17
Add GST on “X-A” (multiplying factor 0.2127)
385.30
TOTAL
2,415.47
Add 15% CPOH on “Y-A”
329.52
TOTAL
2,744.99
Add Cess @ 1% on “Z-A”
25.26
Cost for 0.90 cum.
2,770.25
Cost per cum.
3,078.06
Say
3,078.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1157. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.