Skip to main content
R/DAR 2023

Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required

Water bound macadam
Item number
16.13.2
Analysis basis
Details of cost for 0.90cum.
Priced inputs
11
Derived rate
₹3,078.05
D-01/RATE ANALYSISITEM 16.13.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.13.2 (Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required Water bound macadam) is derived from 11 priced inputs and works out to ₹3,078.05 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a road 6 metres wide and 0.6m.
  • lengthwise and 0.25m cm average depth
  • =0.90cum.
  • Supplying and stacking stone aggregate
  • 53mm to 24mm nominal size at site.
  • Supplying and stacking red bajri at site
  • Supplying and stacking moorum at site.
  • For cutting road and taking out soling and
  • metalling including sorting and screening.
  • For relaying soling stone 3.6x0.15=0.54cum.
  • For relaying road metal with extra quantity
  • and consolidation to 0.10m thickness
  • - 3.6x0.10=0.36cum.
ANALYSIS OF RATES · ITEM 16.13.2DETAILS OF COST FOR 0.90CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 16.3.3 of SH: Road WorkRate as per item 16.3.3cum0.091,842.30165.81
SUBRate as per Item Number 16.3.8 of SH: Road WorkRate as per item 16.3.8cum0.0231,564.9035.99
SUBRate as per Item Number 16.3.10 of SH: Road WorkRate as per item 16.3.10cum0.022768.2516.90
0114LABBeldarday0.48736.00353.28
0115LABCoolieday0.24736.00176.64
0114LABBeldarday0.24736.00176.64
0115LABCoolieday0.24736.00176.64
0114LABBeldarday0.48736.00353.28
0115LABCoolieday0.48736.00353.28
0101LABBhistiday0.1816.0081.60
9999MATBarrier and chowkidar etc.L.S.53.822.27122.17
BUILD-UP TO RATE
TOTAL
2,012.23
Add 1 % Water charges on “W-A”
+17.94
TOTAL
2,030.17
Add GST on “X-A” (multiplying factor 0.2127)
+385.30
TOTAL
2,415.47
Add 15% CPOH on “Y-A”
+329.52
TOTAL
2,744.99
Add Cess @ 1% on “Z-A”
+25.26
Cost for 0.90 cum.
2,770.25
Cost per cum.
3,078.06
SAY
₹3,078.05
D-02/SOURCEPRINTED PAGE 1157
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1157

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1157. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.