Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required
- Item number
- 16.13.1
- Analysis basis
- Details of cost for 1.08cum. (road 6 metres
- Priced inputs
- 15
- Derived rate
- ₹5,032.25
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.13.1 (Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required bituminous portion) is derived from 15 priced inputs and works out to ₹5,032.25 after water charges, GST, CPOH and cess. The full build-up is below.
- wide, 0.6 metre length wise and 0.30m
- (average depth) volume = 1.08 cum).
- Supplying and stacking stone aggregate
- 53mm to 24 mm nominal size at site.
- Supplying and stacking red bajri at site
- Supplying and stacking moorum at site
- Relaying soling stone 3.6x0.15=0.54cum.
- Relaying road metal with extra quantity
- and consolidation to 0.10m, thickness
- 3.6x0.10=0.36cum.
- Painting two coats, 3.6sqm. including labour
- for spreading grit
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 16.3.3 of SH: Road WorkRate as per item 16.3.3 | cum | 0.09 | 1,842.30 | 165.81 | |
| SUB | Rate as per Item Number 16.3.8 of SH: Road WorkRate as per item 16.3.8 | cum | 0.023 | 1,564.90 | 35.99 | |
| SUB | Rate as per Item Number 16.3.10 of SH: Road WorkRate as per item 16.3.10 | cum | 0.022 | 768.25 | 16.90 | |
| 2911 | MAT | Stone chippings/ screenings 10/ 11.2 mm nominal size | cum | 0.092 | 1,400.00 | 128.80 |
| 0309 | MAT | Paving bitumen VG-10 of approved qualityPaving bitumen of grade VG-10 of approved quality | tonne | 0.011 | 33,530.00 | 368.83 |
| 0114 | LAB | Beldar | day | 0.96 | 736.00 | 706.56 |
| 0115 | LAB | Coolie | day | 0.48 | 736.00 | 353.28 |
| 0114 | LAB | Beldar | day | 0.24 | 736.00 | 176.64 |
| 0115 | LAB | Coolie | day | 0.24 | 736.00 | 176.64 |
| 0114 | LAB | Beldar | day | 0.71 | 736.00 | 522.56 |
| 0115 | LAB | Coolie | day | 0.48 | 736.00 | 353.28 |
| 0101 | LAB | Bhisti | day | 0.1 | 816.00 | 81.60 |
| 0114 | LAB | Beldar | day | 0.48 | 736.00 | 353.28 |
| 0115 | LAB | Coolie | day | 0.48 | 736.00 | 353.28 |
| 9999 | MAT | Barrier, chowkidar, sprayman, mate, etc. | L.S. | 40.43 | 2.27 | 91.78 |
- TOTAL
- 3,885.23
- Add 1 % Water charges on “W-A”
- +36.67
- TOTAL
- 3,921.90
- Add GST on “X-A” (multiplying factor 0.2127)
- +787.67
- TOTAL
- 4,709.57
- Add 15% CPOH on “Y-A”
- +673.63
- TOTAL
- 5,383.20
- Add Cess @ 1% on “Z-A”
- +51.65
- Cost for 1.08 cum.
- 5,434.85
- Cost per cum.
- 5,032.27
- SAY
- ₹5,032.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1156
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1156. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.