Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete
- Item number
- 16.12.1
- Analysis basis
- 10 sqm
- Priced inputs
- 4
- Derived rate
- ₹644.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.12.1 (Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 4 priced inputs for 10 sqm and works out to ₹644.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2602 | MAT | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.645 | 4,724.00 | 3,046.98 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.4 | 897.00 | 358.80 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.4 | 816.00 | 326.40 |
| 0114 | LAB | Beldar | day | 1.08 | 736.00 | 794.88 |
- TOTAL
- 4,527.06
- Add 1 % Water charges on “W”
- +45.27
- TOTAL
- 4,572.33
- Add GST on “X” (multiplying factor 0.2127)
- +972.53
- TOTAL
- 5,544.86
- Add 15% CPOH on “Y”
- +831.73
- TOTAL
- 6,376.59
- Add Cess @ 1% on “Z”
- +63.77
- Cost for 10 sqm.
- 6,440.36
- Cost per sqm.
- 644.04
- SAY
- ₹644.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1155
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1155. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.