CPWD Analysis of Rates · Repairs to Buildings
Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal WorkExposed on wall
- Item number
- 14.84
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 1
- Derived rate
- ₹3.25 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.84 — Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal WorkExposed on wall — is derived from 1 priced inputs for 10 metre and works out to ₹3.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | Dismantling of G.I. Pipe and stacking etc.Material | L.S. | 10 | 2.27 | 22.70 |
- TOTAL
- 22.70
- Add 1 % Water charges on “W”
- 0.23
- TOTAL
- 22.93
- Add GST on “X” (multiplying factor 0.2127)
- 4.88
- TOTAL
- 27.81
- Add 15% CPOH on “Y”
- 4.17
- TOTAL
- 31.98
- Add Cess @ 1% on “Z”
- 0.32
- Cost of 10 metres
- 32.30
- Cost of 1 metre
- 3.23
- Say
- 3.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1089. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works