Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal WorkExposed on wall

Item number
14.84
Analysis basis
10 metre
Priced inputs
1
Derived rate
₹3.25/ METRE
D-01/RATE ANALYSISITEM 14.84

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.84 (Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal WorkExposed on wall) is derived from 1 priced inputs for 10 metre and works out to ₹3.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 14.84DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATDismantling of G.I. Pipe and stacking etc.L.S.102.2722.70
BUILD-UP TO RATE
TOTAL
22.70
Add 1 % Water charges on “W”
+0.23
TOTAL
22.93
Add GST on “X” (multiplying factor 0.2127)
+4.88
TOTAL
27.81
Add 15% CPOH on “Y”
+4.17
TOTAL
31.98
Add Cess @ 1% on “Z”
+0.32
Cost of 10 metres
32.30
Cost of 1 metre
3.23
SAY
₹3.25
D-02/SOURCEPRINTED PAGE 1089
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1089

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1089. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.