CPWD Analysis of Rates · Repairs to Buildings

Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal WorkExposed on wall

Item number
14.84
Analysis basis
Details of cost for 10 metre
Priced inputs
1
Derived rate
3.25 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.84 Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineer-in-Charge. (a) Internal WorkExposed on wall — is derived from 1 priced inputs for 10 metre and works out to ₹3.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999Dismantling of G.I. Pipe and stacking etc.MaterialL.S.102.2722.70
TOTAL
22.70
Add 1 % Water charges on “W”
0.23
TOTAL
22.93
Add GST on “X” (multiplying factor 0.2127)
4.88
TOTAL
27.81
Add 15% CPOH on “Y”
4.17
TOTAL
31.98
Add Cess @ 1% on “Z”
0.32
Cost of 10 metres
32.30
Cost of 1 metre
3.23
Say
3.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1089. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.