Taking out existing wooden door shutter, repair by cutting, painting etc. and refixing of repaired door shutters to existing door frames, including replacement of hinges with screws, etc. as required, all complete as per the direction of the Engineer-in-charge
- Item number
- 14.85
- Analysis basis
- one shutter
- Priced inputs
- 3
- Derived rate
- ₹429.10/ ONE SHUTTER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.85 (Taking out existing wooden door shutter, repair by cutting, painting etc. and refixing of repaired door shutters to existing door frames, including replacement of hinges with screws, etc. as required, all complete as per the direction of the Engineer-in-charge) is derived from 3 priced inputs for one shutter and works out to ₹429.10 per one shutter after water charges, GST, CPOH and cess. The full build-up is below.
- Normal exiting size of shutter 1.00x2.02m
- =2.02sqm
- Assuming old hinges fixed in Tee iron frames
- Half qty = 48/2=24 needs replacement
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0637 | MAT | Bright finished or black enameled mild steel screws 40 mm | 100 Nos | 0.24 | 62.00 | 14.88 |
| 0156 | LAB | Carpenter (average) | day | 0.18 | 857.00 | 154.26 |
| 0114 | LAB | Beldar | day | 0.18 | 736.00 | 132.48 |
- TOTAL
- 301.62
- Add 1 % Water charges on “W”
- +3.02
- TOTAL
- 304.64
- Add GST on “X” (multiplying factor 0.2127)
- +64.80
- TOTAL
- 369.44
- Add 15% CPOH on “Y”
- +55.42
- TOTAL
- 424.86
- Add Cess @ 1% on “Z”
- +4.25
- Cost for each shutter
- 429.11
- SAY
- ₹429.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1089
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1089. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.