Taking out existing wooden door shutter, repair by cutting, painting etc. and refixing of repaired door shutters to existing door frames, including replacement of hinges with screws, etc. as required, all complete as per the direction of the Engineer-in-charge

Item number
14.85
Analysis basis
one shutter
Priced inputs
3
Derived rate
₹429.10/ ONE SHUTTER
D-01/RATE ANALYSISITEM 14.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.85 (Taking out existing wooden door shutter, repair by cutting, painting etc. and refixing of repaired door shutters to existing door frames, including replacement of hinges with screws, etc. as required, all complete as per the direction of the Engineer-in-charge) is derived from 3 priced inputs for one shutter and works out to ₹429.10 per one shutter after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Normal exiting size of shutter 1.00x2.02m
  • =2.02sqm
  • Assuming old hinges fixed in Tee iron frames
  • Half qty = 48/2=24 needs replacement
ANALYSIS OF RATES · ITEM 14.85DETAILS OF COST FOR ONE SHUTTER (2.02 SQM)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0637MATBright finished or black enameled mild steel screws 40 mm100 Nos0.2462.0014.88
0156LABCarpenter (average)day0.18857.00154.26
0114LABBeldarday0.18736.00132.48
BUILD-UP TO RATE
TOTAL
301.62
Add 1 % Water charges on “W”
+3.02
TOTAL
304.64
Add GST on “X” (multiplying factor 0.2127)
+64.80
TOTAL
369.44
Add 15% CPOH on “Y”
+55.42
TOTAL
424.86
Add Cess @ 1% on “Z”
+4.25
Cost for each shutter
429.11
SAY
₹429.10
D-02/SOURCEPRINTED PAGE 1089
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1089

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1089. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.