CPWD Analysis of Rates · Repairs to Buildings

Hacking of CC flooring including cleaning for surface etc. complete as per direction of the Engineer-in-Charge

Item number
14.83
Analysis basis
Details of cost for 10 sqm
Priced inputs
2
Derived rate
3.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.83 Hacking of CC flooring including cleaning for surface etc. complete as per direction of the Engineer-in-Charge — is derived from 2 priced inputs for 10 sqm and works out to ₹3.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.03736.0022.08
9999SundriesMaterialL.S.12.272.27
TOTAL
24.35
Add 1 % Water charges on “W”
0.24
TOTAL
24.59
Add GST on “X” (multiplying factor 0.2127)
5.23
TOTAL
29.82
Add 15% CPOH on “Y”
4.47
TOTAL
34.29
Add Cess @ 1% on “Z”
0.34
Cost of 10 sqm
34.63
Cost of 1 sqm
3.46
Say
3.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1088. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.