Hacking of CC flooring including cleaning for surface etc. complete as per direction of the Engineer-in-Charge

Item number
14.83
Analysis basis
10 sqm
Priced inputs
2
Derived rate
₹3.45/ SQM
D-01/RATE ANALYSISITEM 14.83

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.83 (Hacking of CC flooring including cleaning for surface etc. complete as per direction of the Engineer-in-Charge) is derived from 2 priced inputs for 10 sqm and works out to ₹3.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 14.83DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.03736.0022.08
9999MATSundriesL.S.12.272.27
BUILD-UP TO RATE
TOTAL
24.35
Add 1 % Water charges on “W”
+0.24
TOTAL
24.59
Add GST on “X” (multiplying factor 0.2127)
+5.23
TOTAL
29.82
Add 15% CPOH on “Y”
+4.47
TOTAL
34.29
Add Cess @ 1% on “Z”
+0.34
Cost of 10 sqm
34.63
Cost of 1 sqm
3.46
SAY
₹3.45
D-02/SOURCEPRINTED PAGE 1088
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1088

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1088. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.