CPWD Analysis of Rates · Repairs to Buildings

Dismantling W.C. Pan of all sizes including disposal of dismantled materials i/c malba all complete as per directions of Engineer-in-Charge

Item number
14.82
Analysis basis
Details of cost for 1 no.
Priced inputs
2
Derived rate
134.10 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.82 Dismantling W.C. Pan of all sizes including disposal of dismantled materials i/c malba all complete as per directions of Engineer-in-Charge — is derived from 2 priced inputs for 1 no and works out to ₹134.10 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.125736.0092.00
9999SundriesMaterialL.S.12.272.27
TOTAL
94.27
Add 1 % Water charges on “W”
0.94
TOTAL
95.21
Add GST on “X” (multiplying factor 0.2127)
20.25
TOTAL
115.46
Add 15% CPOH on “Y”
17.32
TOTAL
132.78
Add Cess @ 1% on “Z”
1.33
Cost of each
134.11
Say
134.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1088. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works