CPWD Analysis of Rates · Repairs to Buildings

Cutting holes of required size in brick masonry wall for fixing of exhaust fan including providing and fixing 300 mm dia PVC pipe conforming BIS-12818 and making good the same etc. complete as per direction of Engineer-in-charge

Item number
14.81
Analysis basis
Detail of Cost for 10 holes
Priced inputs
7
Derived rate
288.10 / holes

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.81 Cutting holes of required size in brick masonry wall for fixing of exhaust fan including providing and fixing 300 mm dia PVC pipe conforming BIS-12818 and making good the same etc. complete as per direction of Engineer-in-charge — is derived from 7 priced inputs for 10 holes and works out to ₹288.10 per holes after water charges, GST, CPOH and cess. The full build-up is below.

  • Size 0.30x0.30x0.23 m wall
  • 12 mm plaster 1:4 (1 Cement: 4 Coarse sand)
  • Actual Area (10x4x0.3x0.23) = 0.296 + 0.24
  • L.S. For corners/sides = 3.00 Sqm
  • Proportionate labour taken as actually
  • required at site
  • (0.16/0.0306)= 0.11 Nos.
  • (0.16/0.030)x0.207 = 0.11 Nos.
  • (1.25x0.207)/0.0306 =1.10 Nos.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.13.4.1 of SH:FINISHINGRate as per item 13.4.1Sub-analysissqm3357.351,072.05
7752PVC slotted pipe 200 mm dia as per IS: 12818Materialmetre0.25875.00218.75
9999SundriesMaterialL.S.8.062.2718.30
0123Mason 1st classMason 1st classLabourday0.11897.0098.67
0124Mason 2nd classMason 2nd classLabourday0.11816.0089.76
0114BeldarLabourday1.1736.00809.60
9999Add L.S. For DelayMaterialL.S.16.122.2736.59
TOTAL
2,343.72
Add 1 % Water charges on “W-A”
12.72
TOTAL
2,356.44
Add GST on “X-A” (multiplying factor 0.2127)
273.19
TOTAL
2,629.63
Add 15% CPOH on “Y-A”
233.64
TOTAL
2,863.27
Add Cess @ 1% on “Z-A”
17.91
Cost of 10 nos
2,881.18
Cost of each
288.12
Say
288.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1087. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.