R/DAR 2023

Cutting holes of required size in brick masonry wall for fixing of exhaust fan including providing and fixing 300 mm dia PVC pipe conforming BIS-12818 and making good the same etc. complete as per direction of Engineer-in-charge

Item number
14.81
Analysis basis
10 holes
Priced inputs
7
Derived rate
₹288.10/ HOLES
D-01/RATE ANALYSISITEM 14.81

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.81 (Cutting holes of required size in brick masonry wall for fixing of exhaust fan including providing and fixing 300 mm dia PVC pipe conforming BIS-12818 and making good the same etc. complete as per direction of Engineer-in-charge) is derived from 7 priced inputs for 10 holes and works out to ₹288.10 per holes after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Size 0.30x0.30x0.23 m wall
  • 12 mm plaster 1:4 (1 Cement: 4 Coarse sand)
  • Actual Area (10x4x0.3x0.23) = 0.296 + 0.24
  • L.S. For corners/sides = 3.00 Sqm
  • Proportionate labour taken as actually
  • required at site
  • (0.16/0.0306)= 0.11 Nos.
  • (0.16/0.030)x0.207 = 0.11 Nos.
  • (1.25x0.207)/0.0306 =1.10 Nos.
ANALYSIS OF RATES · ITEM 14.81DETAIL OF COST FOR 10 HOLES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.13.4.1 of SH:FINISHINGRate as per item 13.4.1sqm3357.351,072.05
7752MATPVC slotted pipe 200 mm dia as per IS: 12818metre0.25875.00218.75
9999MATSundriesL.S.8.062.2718.30
0123LABMason 1st classMason 1st classday0.11897.0098.67
0124LABMason 2nd classMason 2nd classday0.11816.0089.76
0114LABBeldarday1.1736.00809.60
9999MATAdd L.S. For DelayL.S.16.122.2736.59
BUILD-UP TO RATE
TOTAL
2,343.72
Add 1 % Water charges on “W-A”
+12.72
TOTAL
2,356.44
Add GST on “X-A” (multiplying factor 0.2127)
+273.19
TOTAL
2,629.63
Add 15% CPOH on “Y-A”
+233.64
TOTAL
2,863.27
Add Cess @ 1% on “Z-A”
+17.91
Cost of 10 nos
2,881.18
Cost of each
288.12
SAY
₹288.10
D-02/SOURCEPRINTED PAGE 1087
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1087

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1087. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.