Cutting holes of required size in brick masonry wall for fixing of exhaust fan including providing and fixing 300 mm dia PVC pipe conforming BIS-12818 and making good the same etc. complete as per direction of Engineer-in-charge
- Item number
- 14.81
- Analysis basis
- Detail of Cost for 10 holes
- Priced inputs
- 7
- Derived rate
- ₹288.10 / holes
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.81 — Cutting holes of required size in brick masonry wall for fixing of exhaust fan including providing and fixing 300 mm dia PVC pipe conforming BIS-12818 and making good the same etc. complete as per direction of Engineer-in-charge — is derived from 7 priced inputs for 10 holes and works out to ₹288.10 per holes after water charges, GST, CPOH and cess. The full build-up is below.
- Size 0.30x0.30x0.23 m wall
- 12 mm plaster 1:4 (1 Cement: 4 Coarse sand)
- Actual Area (10x4x0.3x0.23) = 0.296 + 0.24
- L.S. For corners/sides = 3.00 Sqm
- Proportionate labour taken as actually
- required at site
- (0.16/0.0306)= 0.11 Nos.
- (0.16/0.030)x0.207 = 0.11 Nos.
- (1.25x0.207)/0.0306 =1.10 Nos.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.13.4.1 of SH:FINISHINGRate as per item 13.4.1Sub-analysis | sqm | 3 | 357.35 | 1,072.05 | |
| 7752 | PVC slotted pipe 200 mm dia as per IS: 12818Material | metre | 0.25 | 875.00 | 218.75 |
| 9999 | SundriesMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.11 | 897.00 | 98.67 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.11 | 816.00 | 89.76 |
| 0114 | BeldarLabour | day | 1.1 | 736.00 | 809.60 |
| 9999 | Add L.S. For DelayMaterial | L.S. | 16.12 | 2.27 | 36.59 |
- TOTAL
- 2,343.72
- Add 1 % Water charges on “W-A”
- 12.72
- TOTAL
- 2,356.44
- Add GST on “X-A” (multiplying factor 0.2127)
- 273.19
- TOTAL
- 2,629.63
- Add 15% CPOH on “Y-A”
- 233.64
- TOTAL
- 2,863.27
- Add Cess @ 1% on “Z-A”
- 17.91
- Cost of 10 nos
- 2,881.18
- Cost of each
- 288.12
- Say
- 288.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1087. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.