Providing & fixing White vitreous china water closet squatting pan (Indian type) along with “S” or “P” trap including dismantling of old WC seat and “S” or “P” trap at site complete with all operations including all necessary materials, labour and disposal of dismantled material i/c malba, all complete as per the direction of Engineer-in charge

Orissa pattern W.C Pan of size 580x440 mm
Item number
14.80.2
Analysis basis
1 no
Priced inputs
9
Derived rate
₹4,478.75/ NO
D-01/RATE ANALYSISITEM 14.80.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.80.2 (Providing & fixing White vitreous china water closet squatting pan (Indian type) along with “S” or “P” trap including dismantling of old WC seat and “S” or “P” trap at site complete with all operations including all necessary materials, labour and disposal of dismantled material i/c malba, all complete as per the direction of Engineer-in charge Orissa pattern W.C Pan of size 580x440 mm) is derived from 9 priced inputs for 1 no and works out to ₹4,478.75 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (a) For dismantling WC seat and P or S trap
  • (b) For Fixing WC seat and “P” or “S” trap
  • Less for
ANALYSIS OF RATES · ITEM 14.80.2DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1954MATVitreous china orrisa type W.C. pan size 580 mmVitreous china orrisa type W.C. pan of size 580 mmeach11,350.001,350.00
1890MATCentrifugally sand cast (spun) S&S “P” or “S” trapCentrifugally SCI(spun) S & S P or S trapeach1358.00358.00
9999MATCement sand & grit etc.L.S.13.362.2730.33
9977MATCarriage of materialsL.S.13.522.2730.69
1880MATDismantled “P” or “S” trap scrap (app. Wt 2 kg.)Dismenteled P or S trap scrap (approx wt 2kg)kg-228.00-56.00
0129LABSewermanSewer manday0.05736.0036.80
0114LABBeldarday0.125736.0092.00
0126LABMason 1st classMason (for ornamental stone work) 1st classday0.8897.00717.60
0114LABBeldarday0.8736.00588.80
BUILD-UP TO RATE
TOTAL
3,148.22
Add 1 % Water charges on “W”
+31.48
TOTAL
3,179.70
Add GST on “X” (multiplying factor 0.2127)
+676.32
TOTAL
3,856.02
Add 15% CPOH on “Y”
+578.40
TOTAL
4,434.42
Add Cess @ 1% on “Z”
+44.34
Cost of each
4,478.76
SAY
₹4,478.75
D-02/SOURCEPRINTED PAGE 1087
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1087

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1087. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.