Supplying and fixing new wooden fillets wherever necessary

Hollock wood fillets
Item number
14.8.2
Analysis basis
10 metres
Priced inputs
5
Derived rate
₹70.75/ METRE
D-01/RATE ANALYSISITEM 14.8.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.8.2 (Supplying and fixing new wooden fillets wherever necessary: Hollock wood fillets) is derived from 5 priced inputs for 10 metres and works out to ₹70.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10.00x0.01x0.01 = 1.00 cudm
  • Total = 1.15 cudm
  • Add 15% wastage = 0.15 cudm
ANALYSIS OF RATES · ITEM 14.8.2DETAILS OF COST FOR 10 METRES LENGTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2466MATHollock wood in scantling10 cudm0.115366.0042.09
9999MATNailsL.S.26.912.2761.09
0112LABCarpenter 2nd classday0.25816.00204.00
0114LABBeldarday0.25736.00184.00
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
497.38
Add 1 % Water charges on “W”
+4.97
TOTAL
502.35
Add GST on “X” (multiplying factor 0.2127)
+106.85
TOTAL
609.20
Add 15% CPOH on “Y”
+91.38
TOTAL
700.58
Add Cess @ 1% on “Z”
+7.01
Cost of 10.00 metre
707.59
Cost of 1.00 metre
70.76
SAY
₹70.75
D-02/SOURCEPRINTED PAGE 1046
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1046

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1046. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.