Supplying and fixing new wooden fillets wherever necessary

2nd class teak wood fillets
Item number
14.8.1
Analysis basis
10 metres
Priced inputs
5
Derived rate
₹77.70/ METRE
D-01/RATE ANALYSISITEM 14.8.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.8.1 (Supplying and fixing new wooden fillets wherever necessary: 2nd class teak wood fillets) is derived from 5 priced inputs for 10 metres and works out to ₹77.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10.00x0.01x0.01 = 1.00 cudm
  • Total = 1.15 cudm
  • Add 15% wastage = 0.15 cudm
ANALYSIS OF RATES · ITEM 14.8.1DETAILS OF COST FOR 10 METRES LENGTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1190MATSecond class teak wood in planks10 cudm0.115791.0090.97
9999MATNailsL.S.26.912.2761.09
0112LABCarpenter 2nd classday0.25816.00204.00
0114LABBeldarday0.25736.00184.00
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
546.26
Add 1 % Water charges on “W”
+5.46
TOTAL
551.72
Add GST on “X” (multiplying factor 0.2127)
+117.35
TOTAL
669.07
Add 15% CPOH on “Y”
+100.36
TOTAL
769.43
Add Cess @ 1% on “Z”
+7.69
Cost of 10.00 metre
777.12
Cost of 1.00 metre
77.71
SAY
₹77.70
D-02/SOURCEPRINTED PAGE 1046
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1046

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1046. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.