CPWD Analysis of Rates · Repairs to Buildings

Cleaning of under ground sump, Over Head R.C.C. Tank ( independent staging) including disposal of slit and rubbish, all as per direction of Engineer-in-Charge. The cleaning shall consist following operations:- (i) Tank shall be emptied of water by pumping & bottom shall be cleaned of silt and other deposits. (ii) Entire surface area of the sump shall then scrubbed thoroughly with wire brush etc. and pressure washed with water. (iii) Chlorination of RCC internal surface by liquid chlorine. (iv) The treated surface shall be dried using air jetting and all loose particles shall be removal from the surface. (v) Finally the surface shall be treated with ultraviolet radiation etc. as per direction of Engineer-in-Charge

Item number
14.78
Priced inputs
13
Derived rate
84.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.78 Cleaning of under ground sump, Over Head R.C.C. Tank ( independent staging) including disposal of slit and rubbish, all as per direction of Engineer-in-Charge. The cleaning shall consist following operations:- (i) Tank shall be emptied of water by pumping & bottom shall be cleaned of silt and other deposits. (ii) Entire surface area of the sump shall then scrubbed thoroughly with wire brush etc. and pressure washed with water. (iii) Chlorination of RCC internal surface by liquid chlorine. (iv) The treated surface shall be dried using air jetting and all loose particles shall be removal from the surface. (v) Finally the surface shall be treated with ultraviolet radiation etc. as per direction of Engineer-in-Charge — is derived from 13 priced inputs and works out to ₹84.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Let a underground tank of capacity 272000
  • litre or 272 KL and area of tank is 570sqm
  • (a) Dewater and slit cleaning
  • Considering through pumping 20% of
  • water to be lifted, water discharge =(272 x
  • 20/100=54.40KL)
  • 4000 litres per hours , = (54.4/4 =13.6 hours =
  • @ 8 hours/ day = 1.7 day)
  • (b) Scrabing the internal surface of tank
  • (c) Bleaching
  • (d) Air jetting
  • (e) Ultra Violet Radiation
  • Cost of pumping water with pump of capacity
CodeInputUnitQuantityRate (INR)Amount (INR)
0011Hire charges of Pump set of capacity 4000 litres/hourMachineryday1.7800.001,360.00
0114BeldarLabourday10.88736.008,007.68
0114BeldarLabourday5.13736.003,775.68
0115CoolieLabourday2.28736.001,678.08
0101BhistiLabourday2.28816.001,860.48
9999SundriesMaterialL.S.142.52.27323.48
1301Bleaching powderMaterialquintal0.571,700.00969.00
0006Hire charges of Spraying machine including electric chargesMachineryday14.25250.003,562.50
0138Sprayer (for bitumen, tar etc.)Labourday14.25816.0011,628.00
0058Air compressorMachineryhour2250.00500.00
0114BeldarLabourday0.25736.00184.00
0085Using cost of Ultra Violet Radiation tubeMachineryhour0.5200.00100.00
0114BeldarLabourday0.063736.0046.37
TOTAL
33,995.27
Add 1 % Water charges on “W”
339.95
TOTAL
34,335.22
Add GST on “X” (multiplying factor 0.2127)
7,303.10
TOTAL
41,638.32
Add 15% CPOH on “Y”
6,245.75
TOTAL
47,884.07
Add Cess @ 1% on “Z”
478.84
Cost of 570 sqm
48,362.91
Cost of 1 sqm
84.85
Say
84.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1085. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works