Cleaning of chocked sewer line by diesel running vehicle mounting hydraulic operated high pressure suction cum jetting sewer cleaning machine fitted with pump having 4000 litres suction capacity and 6000 litres water jetting tank capacity including skilled operator, supervising engineer etc. for cleaning and partial desilting of manholes and dechocking of sewer lines. Dechocking and flushing of sewer line from one manhole to another by high pressure jetting system of 2200 PSI for sewer line from 150mm dia upto 300mm
- Item number
- 14.77
- Analysis basis
- 208 metre
- Priced inputs
- 5
- Derived rate
- ₹340.75/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.77 (Cleaning of chocked sewer line by diesel running vehicle mounting hydraulic operated high pressure suction cum jetting sewer cleaning machine fitted with pump having 4000 litres suction capacity and 6000 litres water jetting tank capacity including skilled operator, supervising engineer etc. for cleaning and partial desilting of manholes and dechocking of sewer lines. Dechocking and flushing of sewer line from one manhole to another by high pressure jetting system of 2200 PSI for sewer line from 150mm dia upto 300mm) is derived from 5 priced inputs for 208 metre and works out to ₹340.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Machineries
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Soap, brush, cloths & sundries | L.S. | 345 | 2.27 | 783.15 |
| 8500 | MAT | Water for jetting / blowback | 1000 litre | 0.002 | 1,450.00 | 2.90 |
| 0087 | MACH | Hire Charges of Suction Jeting machine 2200 PSI machine i/c POL and operator | day | 1 | 44,800.00 | 44,800.00 |
| 0139 | LAB | Skilled Beldar (for floor rubbing etc.) | day | 4 | 816.00 | 3,264.00 |
| 0160 | LAB | Technician | day | 1 | 973.00 | 973.00 |
- TOTAL
- 49,823.05
- Add 1 % Water charges on “W”
- +498.23
- TOTAL
- 50,321.28
- Add GST on “X” (multiplying factor 0.2127)
- +10,703.34
- TOTAL
- 61,024.62
- Add 15% CPOH on “Y”
- +9,153.69
- TOTAL
- 70,178.31
- Add Cess @ 1% on “Z”
- +701.78
- Cost of 208 metre
- 70,880.09
- Cost of 1.00 metre
- 340.77
- SAY
- ₹340.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1084
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1084. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.