Renewing glass panes, with putty and nails wherever necessary including racking out the old putty

Float glass panes of nominal thickness 4 mm (weight not less than 10kg/sqm)

Item number
14.5.1
Analysis basis
Detail of cost for 10 glasses area each
Priced inputs
8
Derived rate
1,090.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.5.1 Renewing glass panes, with putty and nails wherever necessary including racking out the old putty: Float glass panes of nominal thickness 4 mm (weight not less than 10kg/sqm) — is derived from 8 priced inputs for 10 glasses and works out to ₹1,090.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 0.1sqm.
  • 1.00 sqm + 10% wastage= 1.10 Sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2406Float glass panes of nominal thickness 4 mm (weight not less than 10kg/sqm)Float glass panes of nominal thickness 4 mm (weight not less than 10 kg/sqm)Materialsqm1.1321.00353.10
9988Carriage including sundriesMaterialL.S.1.822.274.13
0863Putty for wood workMaterialkilogram0.6832.0021.76
9999Painting or varnishing or beewaxingMaterialL.S.5.332.2712.10
9999Sundries Nails etc.MaterialL.S.6.762.2715.35
0119GlazierLabourday0.23816.00187.68
0114BeldarLabourday0.23736.00169.28
9999Sundries such as Rag, cotton etcMaterialL.S.1.432.273.25
TOTAL
766.65
Add 1 % Water charges on “W”
7.67
TOTAL
774.32
Add GST on “X” (multiplying factor 0.2127)
164.70
TOTAL
939.02
Add 15% CPOH on “Y”
140.85
TOTAL
1,079.87
Add Cess @ 1% on “Z”
10.80
Cost of 1.00 sqm
1,090.67
Say
1,090.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 9999. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.