CPWD Analysis of Rates · Repairs to Buildings
Making the opening in brick masonry including dismantling in floor or walls by cutting masonry and making good the damages to walls, flooring and jambs complete, to match existing surface i/c disposal of mulba/ rubbish to the nearest municipal dumping ground, all complete as per direction of Engineer-in-Charge
For door/ window/ clerestory window
- Item number
- 14.4.1
- Analysis basis
- Details of cost for one opening of size
- Priced inputs
- 6
- Derived rate
- ₹1,264.35 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.4.1 — Making the opening in brick masonry including dismantling in floor or walls by cutting masonry and making good the damages to walls, flooring and jambs complete, to match existing surface i/c disposal of mulba/ rubbish to the nearest municipal dumping ground, all complete as per direction of Engineer-in-Charge For door/ window/ clerestory window — is derived from 6 priced inputs for one opening and works out to ₹1,264.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 0.90x2.10m = 1.89 sqm
- Cement mortar 1:6 (1 cement: 6 fine sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 3.6 of SH: MortarsRate as per item 3.6Sub-analysis | cum | 0.01 | 3,038.50 | 30.39 | |
| 9999 | Cement concrete 1:2:4 filled in chase cutMaterial | L.S. | 24.57 | 2.27 | 55.77 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0114 | BeldarLabour | day | 1.2 | 736.00 | 883.20 |
| 0115 | CoolieLabour | day | 0.4 | 736.00 | 294.40 |
| 9999 | Scaffolding and SundriesMaterial | L.S. | 3.5 | 2.27 | 7.95 |
- TOTAL
- 1,679.71
- Add 1 % Water charges on “W”
- 16.80
- TOTAL
- 1,696.51
- Add GST on “X” (multiplying factor 0.2127)
- 360.85
- TOTAL
- 2,057.36
- Add 15% CPOH on “Y”
- 308.60
- TOTAL
- 2,365.96
- Add Cess @ 1% on “Z”
- 23.66
- Cost of 1.89sqm.
- 2,389.62
- Cost of 1.00 sqm.
- 1,264.35
- Say
- 1,264.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1042. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.