Providing and fixing plain jaffri door and window shutters including bright or/and black enamelled M.S. butt hinges with necessary screws 35x10 mm laths placed 35 mm apart (frames to be paid separately), including fixing 50x12 mm beading complete with

Second class teak wood
Item number
14.27.1
Analysis basis
Details of cost of a jaffri shutter 176x86 cm =
Priced inputs
7
Derived rate
₹4,602.65/ SQM
D-01/RATE ANALYSISITEM 14.27.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.27.1 (Providing and fixing plain jaffri door and window shutters including bright or/and black enamelled M.S. butt hinges with necessary screws 35x10 mm laths placed 35 mm apart (frames to be paid separately), including fixing 50x12 mm beading complete with : Second class teak wood) is derived from 7 priced inputs and works out to ₹4,602.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.51 sqm
  • Teak wood 2nd class
  • Styles 2x176x7.5x3.5 cm = 0.0092 cum
  • Rails 3x86x7.5x3.5 = 0.0068 cum
  • Total = 0.0176 cum Say 18 cudm
  • Palain Jaffri work
  • For making frame and fixing fitting
  • Total 0.0160 cum
  • Add wastage @ 10 % =0.0016 cum
ANALYSIS OF RATES · ITEM 14.27.1DETAILS OF COST OF A JAFFRI SHUTTER 176X86 CM =
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1190MATSecond class teak wood in planks10 cudm1.8791.001,423.80
SUBRate as per Item Number 9.41.1 of SH:Wood and PVC workRate as per item 9.41.1sqm1.512,945.104,447.10
0595MATBright finished or black enamelled mild steel butt hinges 100x58x1.90 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 100x58x 1.90 mm10 Nos0.680.0048.00
0597MATBright finished or black enamelled mild steel butt hinges50x37x1.50 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 50x37x 1.50 mm10 Nos0.249.009.80
0637MATBright finished or black enamelled mild steel screws 40 mmBright finished or black enameled mild steel screws 40 mm100 Nos0.4862.0029.76
0640MATBright finished or black enamelled mild steel screws 20 mmBright finished or black enameled mild steel screws 20 mm100 Nos0.0840.003.20
0112LABCarpenter 2nd classday0.3816.00244.80
BUILD-UP TO RATE
TOTAL
6,206.46
Add 1 % Water charges on “W-A”
+17.59
TOTAL
6,224.05
Add GST on “X-A” (multiplying factor 0.2127)
+377.96
TOTAL
6,602.01
Add 15% CPOH on “Y-A”
+323.24
TOTAL
6,925.25
Add Cess @ 1% on “Z-A”
+24.78
Cost of 1.51 sqm.
6,950.03
Cost of 1 sqm.
4,602.67
SAY
₹4,602.65
D-02/SOURCEPRINTED PAGE 1066
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1066

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1066. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.