CPWD Analysis of Rates · Repairs to Buildings
Providing and fixing brass curtain rods of wall thickness 1.25 mm with two brass brackets fixed with brass screws and wooden plugs etc. wherever necessary complete
20 mm diameter
- Item number
- 14.28.1
- Analysis basis
- Detail of cost for 2 metre long
- Priced inputs
- 7
- Derived rate
- ₹343.50 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.28.1 — Providing and fixing brass curtain rods of wall thickness 1.25 mm with two brass brackets fixed with brass screws and wooden plugs etc. wherever necessary complete 20 mm diameter — is derived from 7 priced inputs for 2 metre and works out to ₹343.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Wooden plugs including cutting brick work
- and fixing in cement mortar
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0444 | Brass curtain rod 20 mm dia 1.25 mm thickMaterial | metre | 2 | 154.00 | 308.00 |
| 0446 | Brass brackets (curtain rods) 20 mmMaterial | each | 2 | 49.00 | 98.00 |
| 9999 | ScrewsMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9977 | CarriageMaterial | L.S. | 1.56 | 2.27 | 3.54 |
| Rate as per item no 9.32 of SH : Wood workRate as per item 8.23Sub-analysis | each | 2 | 40.85 | 81.70 | |
| 9999 | LABOURMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | SundriesMaterial | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 507.18
- Add 1 % Water charges on “W-A”
- 4.25
- TOTAL
- 511.43
- Add GST on “X-A” (multiplying factor 0.2127)
- 91.40
- TOTAL
- 602.83
- Add 15% CPOH on “Y-A”
- 78.17
- TOTAL
- 681.00
- Add Cess @ 1% on “Z-A”
- 5.99
- Cost of 2 metre
- 686.99
- Cost of 1 metre
- 343.50
- Say
- 343.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1067. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.