Providing and fixing brass curtain rods of wall thickness 1.25 mm with two brass brackets fixed with brass screws and wooden plugs etc. wherever necessary complete
- Item number
- 14.28.1
- Analysis basis
- 2 metre
- Priced inputs
- 7
- Derived rate
- ₹343.50/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.28.1 (Providing and fixing brass curtain rods of wall thickness 1.25 mm with two brass brackets fixed with brass screws and wooden plugs etc. wherever necessary complete 20 mm diameter) is derived from 7 priced inputs for 2 metre and works out to ₹343.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Wooden plugs including cutting brick work
- and fixing in cement mortar
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0444 | MAT | Brass curtain rod 20 mm dia 1.25 mm thick | metre | 2 | 154.00 | 308.00 |
| 0446 | MAT | Brass brackets (curtain rods) 20 mm | each | 2 | 49.00 | 98.00 |
| 9999 | MAT | Screws | L.S. | 2.73 | 2.27 | 6.20 |
| 9977 | MAT | Carriage | L.S. | 1.56 | 2.27 | 3.54 |
| SUB | Rate as per item no 9.32 of SH : Wood workRate as per item 8.23 | each | 2 | 40.85 | 81.70 | |
| 9999 | MAT | LABOUR | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | MAT | Sundries | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 507.18
- Add 1 % Water charges on “W-A”
- +4.25
- TOTAL
- 511.43
- Add GST on “X-A” (multiplying factor 0.2127)
- +91.40
- TOTAL
- 602.83
- Add 15% CPOH on “Y-A”
- +78.17
- TOTAL
- 681.00
- Add Cess @ 1% on “Z-A”
- +5.99
- Cost of 2 metre
- 686.99
- Cost of 1 metre
- 343.50
- SAY
- ₹343.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1067
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1067. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.