Providing and fixing brass curtain rods of wall thickness 1.25 mm with two brass brackets fixed with brass screws and wooden plugs etc. wherever necessary complete

20 mm diameter
Item number
14.28.1
Analysis basis
2 metre
Priced inputs
7
Derived rate
₹343.50/ METRE
D-01/RATE ANALYSISITEM 14.28.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.28.1 (Providing and fixing brass curtain rods of wall thickness 1.25 mm with two brass brackets fixed with brass screws and wooden plugs etc. wherever necessary complete 20 mm diameter) is derived from 7 priced inputs for 2 metre and works out to ₹343.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Wooden plugs including cutting brick work
  • and fixing in cement mortar
ANALYSIS OF RATES · ITEM 14.28.1DETAIL OF COST FOR 2 METRE LONG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0444MATBrass curtain rod 20 mm dia 1.25 mm thickmetre2154.00308.00
0446MATBrass brackets (curtain rods) 20 mmeach249.0098.00
9999MATScrewsL.S.2.732.276.20
9977MATCarriageL.S.1.562.273.54
SUBRate as per item no 9.32 of SH : Wood workRate as per item 8.23each240.8581.70
9999MATLABOURL.S.2.732.276.20
9999MATSundriesL.S.1.562.273.54
BUILD-UP TO RATE
TOTAL
507.18
Add 1 % Water charges on “W-A”
+4.25
TOTAL
511.43
Add GST on “X-A” (multiplying factor 0.2127)
+91.40
TOTAL
602.83
Add 15% CPOH on “Y-A”
+78.17
TOTAL
681.00
Add Cess @ 1% on “Z-A”
+5.99
Cost of 2 metre
686.99
Cost of 1 metre
343.50
SAY
₹343.50
D-02/SOURCEPRINTED PAGE 1067
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1067

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1067. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.