Brick work with common burnt clay bricks of class designation 7.5 in mud mortar
- Item number
- 14.25
- Analysis basis
- 1 cum
- Priced inputs
- 7
- Derived rate
- ₹6,207.25/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.25 (Brick work with common burnt clay bricks of class designation 7.5 in mud mortar) is derived from 7 priced inputs for 1 cum and works out to ₹6,207.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Mud mortar
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2602 | MAT | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.494 | 4,724.00 | 2,333.66 |
| SUB | Rate as per Item Number 3.18 of SH: MortarsRate as per item 3.18 | cum | 0.25 | 940.55 | 235.14 | |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.36 | 897.00 | 322.92 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.36 | 816.00 | 293.76 |
| 0115 | LAB | Coolie | day | 1.37 | 736.00 | 1,008.32 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
- TOTAL
- 4,363.20
- Add 1 % Water charges on “W”
- +43.63
- TOTAL
- 4,406.83
- Add GST on “X” (multiplying factor 0.2127)
- +937.33
- TOTAL
- 5,344.16
- Add 15% CPOH on “Y”
- +801.62
- TOTAL
- 6,145.78
- Add Cess @ 1% on “Z”
- +61.46
- Cost of 1 Cum.
- 6,207.24
- SAY
- ₹6,207.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1062
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1062. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.