Pumping out water caused by springs, tidal or river seepage, broken water mains or drains and the like
- Item number
- 14.23
- Priced inputs
- 2
- Derived rate
- ₹231.05/ KILOLITRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.23 (Pumping out water caused by springs, tidal or river seepage, broken water mains or drains and the like) is derived from 2 priced inputs and works out to ₹231.05 per kilolitre after water charges, GST, CPOH and cess. The full build-up is below.
- Details for 10.91 kilolitre
- Pumping hours 3 hrs. or 0.375 days
- for clearing slush
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0011 | MACH | Hire charges of Pumpset of capacity 4000 litres/hourHire charges of Pump set of capacity 4000 litres/hour | day | 0.375 | 800.00 | 300.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
- TOTAL
- 1,772.00
- Add 1 % Water charges on “W”
- +17.72
- TOTAL
- 1,789.72
- Add GST on “X” (multiplying factor 0.2127)
- +380.67
- TOTAL
- 2,170.39
- Add 15% CPOH on “Y”
- +325.56
- TOTAL
- 2,495.95
- Add Cess @ 1% on “Z”
- +24.96
- Cost of 10.91 kilolitre
- 2,520.91
- Cost of 1 kilolitre
- 231.06
- SAY
- ₹231.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1061
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1061. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.